The Municipal and Sanitary Engineer's HandbookBoulnois, H. Percy (Henry Percy)
Science
The Municipal and Sanitary Engineer's Handbook
Boulnois, H. Percy (Henry Percy)
Municipal engineering; Sanitary engineering
“It will in all cases be necessary, upon application being made for
sanction to a loan, for the execution of works, that plans (or tracings
of the plans), sections, estimates in detail and specifications be
submitted with the application, accompanied by information as to the
population at the two last periods of the taking of the census, the
rateable value of the district, and the amount of outstanding loans.”
“Such plans or tracings may be used for showing lines of main sewers,
drains, water-pipes and gas-mains. The lines of main sewers and drains
should have the cross sectional dimensions of the sewers and their
gradients distinctly marked (written and figured) upon them. The
dimensions of water and gas pipes should also be shown in figures or by
writing.”
“N.B.--No general map should be submitted which is drawn to a scale of
less than 6 inches to a mile, except when the inch ordnance map is
used.”
“Maps upon which sewerage works or water works are to be shown, or for
street improvements, should be not less than the ordnance scale of
¹⁄₂₅₀₀th.”
“The sections should be drawn to the same horizontal scale, and to a
vertical scale of 20 feet to 1 inch.”
Any detailed plan for the purposes of house drainage, paving, the
purchase of land &c., should be “constructed to a scale of not less than
10 feet to a mile, and upon this plan should be exhibited all houses and
other buildings, bench marks, the levels of streets and roads, of
cellars, of the sea at high and low tide level, and the summer and
flood levels of rivers. 3 feet by 2 feet will be a convenient size for
the sheets of this plan.”
“Enlarged detail plans and sections of sewers, side entrances,
man-holes, sewer sluices, sluice valves, water-pipe joints, and similar
details, should be to a scale not less than 8 feet to 1 inch, and for
some details 4 feet to 1 inch.”[250]
“As it may occasionally be desired to carry out works piecemeal, with a
view to save the time which would be occupied in the preparation of a
complete plan from actual survey, it will be sufficient in the first
instance to furnish any available general plan of streets and roads,
with the surface levels and those of the deepest cellars figured in feet
and inches, and the proposed scheme of works shown (or sketched)
thereon, after which the works can proceed in sections. It should be
understood, however, that a complete plan of the entire district must be
proceeded with, so that when the works are finished, the sanitary
authority and this Board may possess a proper record of them.”
And again, Mr. Rawlinson in the same year, at a meeting of the
Association of Municipal and Sanitary Engineers, writes as follows:
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account