Geology -- Egypt; Nile River; Water-supply -- Egypt
About two years later Mr. Cope Whitehouse suggested utilising the Wadi
Rayan depression as a reservoir. This depression had been already
mentioned by Linant Pasha in his book and located by him on his
hydrological map. Financial difficulties prevented Sir Colin
Scott-Moncrieff from immediately considering the question of reservoirs.
The success of the Barrage repairs in 1887 however gave new life to the
question of reservoirs and Sir Colin Scott-Moncrieff deputed Col.
Western to give scope to the suggestion made by Mr. Cope Whitehouse, to
make plans of the Wady Rayan and the deserts between it and the Nile, to
find out the capacity of the reservoir, and see if it could be utilised.
Col. Western’s report, plans and estimates were printed by the Egyptian
Government in 1888. At the same time I was deputed to examine the other
projects of Count de la Motte. In 1889 and 1891 I reported unfavourably
on them, because I could find no depression near Kalabsha to put in
communication with the Nile, and could find no rock at Silsila on which
to build a dam. The Bergat Takham pan was the only depression near
Kalabsha which could have been used as a reservoir and it was over 100
metres above the level of the Nile flood; while both in the Silsila pass
and the Silsila gate I bored for rock and was everywhere still in sand
10 metres below the level at which the existence of rock was assumed by
the Count’s engineers. On my report reaching Cairo, M. Prompt proposed
using the trough of the Nile itself at Kalabsha as a reservoir in place
of the depression which did not exist. Col. Western left the country in
1890 and I became Director General of Reservoir Studies. M. Prompt had
supposed that rock could be met with at Kalabsha at a depth of 4 metres
below low-water level. I could not find it at a depth of 26 metres.
After sounding and boring at every possible site on the Nile and
surveying, boring, and levelling in the desert between Wadi Halfa and
the Fayoum, I submitted my report in 1894, proposing an open dam at
Assouan of a type which I trusted would meet the requirements of a Nile
reservoir dam. Sir William Garstin approved of the site and the design,
and the dam was built between 1898 and 1902 with Mr. Maurice Fitzmaurice
C.M.G, as resident engineer.
The Assouan Reservoir at its present level contains one milliard of
cubic metres of water which will suffice for the conversion of half a
million acres to perennial irrigation, adding £15,000,000 to the wealth
of the country. But though the dam was only completed at the end of
1902, already the whole of the water has been devoted to special tracts,
and the Government is reluctantly compelled to refuse all applications
for water.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account