This incident impressed Sir Charles Metcalfe, and, after a chat with
the English overseers, foremen and engineers surveying the placing of
the 33-feet lengths of steel upon the ground, it was decided to make an
experiment just to see what could be accomplished under an emergency
with native labour. The black men were marshalled up for a full day’s
work, and were urged to let themselves go, the desire of establishing a
record being communicated to the more enterprising spirits. The natives
love a contest, and they girdled into the work with astonishing zest.
They did not seem to tire, and they spurned the heat. The result was
that when the ten hours’ labour was completed for the day the steel had
crept forward no less that 5¾ miles--a world’s record. Yet everything
proceeded so smoothly that it appeared, from the stranger’s point of
view, as if work were being carried out at the normal rate of a mile a
day.
This result, with native labour, was remarkable. The engineers in
charge of the wonderful track-layer used in America point to the speed
with which the metals can be laid with its aid. Yet it comes somewhat
as a shock to their pride to learn that their best performances of 3 to
4½ miles a day can be exceeded by unskilled black men, with no tools
whatever.
From Kalomo the engineers pushed north-eastwards to Broken Hill,
280 miles beyond. In this stretch, however, another obstacle had to
be overcome. This was the Kafue River, which is the most important
tributary to the Zambesi River, and indeed forms one leg of this great
waterway. The great width of the Kafue River, 1,300 feet, called for a
lengthy bridge. Although the waters are shallow during the dry season,
the average depth being 9 feet, in the wet season, however, the river
rises to 17 feet or so. It is a comparatively sluggish waterway, the
speed of the current being about 3 miles an hour.
Mr. G. A. Hobson was responsible for the design of this bridge also,
and he decided that a light structure, divided into 13 spans each of
100 feet, would meet the case. The actual construction was carried
out by Mr. A. L. Lawley as supervising engineer on behalf of the
railway-builders. The bridge is of the lattice girder type, the trains
running through the bridge. The whole of the steel-work was prepared
in England, shipped to Cape Town, and then transported 2000 miles up
country by railway to a yard improvised on the river bank, where the
ribs of steel were assembled to form the spans. In addition, a pontoon,
likewise of steel, was sent up in pieces in a similar manner, assembled
on the bank and launched. This pontoon was utilised to float the spans
into position, and also to convey material across the river to enable
the grade to be pushed ahead while the waterway was being spanned. The
pontoon was pulled from bank to bank by means of an endless wire cable,
driven by a steam engine.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account