The Railway Conquest of the WorldTalbot, Frederick Arthur Ambrose
History
The Railway Conquest of the World
Talbot, Frederick Arthur Ambrose
Railroad engineering -- History; Railroads -- History
In the summer the watercourse is dry. Note the measures adopted to
protect the piers from the force of the flood waters.
TWO VIEWS ON THE SOUTH AUSTRALIAN GOVERNMENT RAILWAYS]
The task was commenced in July 1908 under the guidance of Mr. James
Fraser, M.INST.C.E., the engineer-in-chief for existing lines, to whom
I am indebted for this information, and in a short time 1000 men were
engaged in boring the tunnels and making the deep, heavy cuts through
the sandstone rock. All tunnels were attacked simultaneously, and
the blasting assumed heavy proportions. In one case a shaft was sunk
practically to formation-level. When completed it was charged with
about 10,000 pounds of blasting powder and 125 pounds of gelignite.
It was fired electrically, and the splitting force of the explosives
dislodged 35,000 tons of rock. In another case 1000 pounds of blasting
powder were tamped home in the face of a cliff, and 10,000 tons of rock
were shivered to be used for embanking purposes.
In order to rush the work through at tip-top speed, special
arrangements were made to facilitate the handling of the necessary
supplies and men, as well as the operation of the tools. As the new
line passed 350 feet below the old line, connection between the two at
this crossing was effected by means of a funicular railway with a grade
of 1 in 1.87. The material was brought by rail to the upper end of this
temporary line, and from a special siding was dispatched direct on to
the works. A small electric generating station was set up, and wires
for the transmission of current for power and lighting were strung
along the route from end to end to compress the air to drive the rock
drills, for the motors actuating the ventilating fans and also the
water-pumps.
The scheme as originally planned provided for the building of 6 miles
858 yards of new double track, which represented a saving of 22 yards
upon the line that was being displaced, though the curves and grades
were easier. It was estimated that the earthworks would involve the
handling of 466,000 cubic yards apart from the tunnel borings. Eleven
tunnels were planned, representing a total length of 2,991 yards,
but during the work it was decided to cut out one tunnel as the rock
was found to be shattered. Consequently it was converted into an open
cutting, the sides of which are 132 feet high. Some idea of the speed
with which the task was pushed forward may be gauged from the fact that
in 11 months 410,000 cubic yards of excavation were completed, 1¼ miles
of permanent way were laid with a single line, and 1,430 yards of the
tunnelling were completed. The total cost of the work was estimated at
£256,000, or $1,280,000. Its recent completion, although it relegates
an imposing engineering achievement to the limbo of things that were,
has resulted in the creation of another achievement equally as notable.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account