In 1870 the task of laying some 2,500 miles of track was commenced. The
mouth of the Columbia River was selected as the outlet on the Pacific
Ocean. Work was commenced simultaneously from both ends, the eastern
terminal being near Lake Superior. By 1873 the line had reached the
Missouri River on the east, and here a pause had to be called to erect
a massive steel bridge, 1,400 feet long, 50 feet above the river, which
absorbed £200,000, or $1,000,000.
When the first stretch of prairie line was completed, it was used only
in the summer months. There was not enough traffic to pay for the coal
burned in the locomotives during the winter, in the estimation of the
administration, while they feared the expense and losses that would be
inflicted by the terrible blizzards and snowstorms which rage in this
country. Consequently, after the crops had been garnered and conveyed
to market, all the engines, trucks and cars were withdrawn from service
upon a great length of line, which was abandoned practically until
spring came round.
This state of affairs continued until the Indians rose up against
American law and order, wiped out several men, and precipitated a
general reign of terror. The Government, in order to pour troops into
the disaffected territory, requested the working of the railway during
the winter of 1876–7, which proved to be one of the most severe in
history. Yet the line suffered less from snow than the systems in the
eastern States, and, moreover, possibilities of traffic were discovered
which hitherto had been considered non-existent. Needless to say, the
railway never has been closed during the winter since.
Before the railway had proceeded half-way across the continent, the
need for overhauling and relaying the first part of the track was felt.
A higher standard of construction was therefore laid down for all the
new work. Moreover, in order that the line should be completed within
the shortest time possible, it was split into large sections, and the
grade was driven east and west from several points simultaneously.
[Illustration: THE “SWITCHBACK” BY MEANS OF WHICH THE GREAT NORTHERN
RAILWAY OF THE UNITED STATES NEGOTIATED THE CASCADE MOUNTAINS BEFORE
THE BORING OF THE CASCADE TUNNEL]
The mountains proved a severe stumbling-block and precipitated great
delay. The country was so broken that lofty timber trestles had to be
erected to be filled in with earth at a later date. Then two large
tunnels had to be bored to carry the track through the Rockies, one,
the Bozeman tunnel, being 3,610 feet long, and the other, the Mullan
tunnel, 3,857 feet from end to end. Yet construction proceeded so
successfully that the links were joined up on September 3, 1883, the
last spike being driven in Hellgate Canyon, Montana. The spike used
for this auspicious event was the very first that had been driven in
connection with the line when it was commenced years before.
[Illustration: BUILDING A STEEL TRESTLE ACROSS A RIFT
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account