At the beginning of the war the Prussian General Staff had (according to
Rüstow) assumed that Metz would offer a prolonged resistance, and that
the defenders would be certain to make an attempt to interrupt the rail
communication between Germany and her troops in the field. To meet the
position which might thus be created, it was decided to build from Pont
à Mousson to Remilly a field railway which, avoiding Metz, would link up
at Remilly with the line proceeding thence to Saarbrück, and so ensure
the maintenance of direct rail communication to and from Germany. On
August 14, 1870, the day of the rearguard action at Borny, the survey
and the levelling of the ground were begun, and three days later a start
was made with the construction. Altogether some 4,200 men were employed
on the work, namely, 400 belonging to two Field Railway Companies; 800
forming four Fortress Pioneer Companies, and about 3,000 miners from the
colliery districts of Saarbrück who had been thrown out of work owing to
the war and accepted employment on the railway. The building corps had
at their disposal a park of 330 wagons and other vehicles, and patrol
and requisition duties were performed for them by a squadron of Cavalry.
Notwithstanding that so considerable a force was available for the
purpose, the work of building the twenty-two miles of railway took
forty-eight days, the line not being ready for operation until October
4. This was in no way a great achievement, and it did not compare
favourably with much that was done by the Federal Construction Corps
employed in the American War of Secession. It is true that the
irregularities of the ground were such as to render necessary numerous
cuttings and embankments, and that two bridges and two viaducts had
to be provided; but the cuttings were only about 3 feet deep, and the
embankments were only 5 feet high, except near one of the viaducts,
where they were 10 feet high. The viaducts and bridges were of timber,
with spans of about 16 feet. The building of the line was, therefore, in
no way a formidable undertaking, from an engineering point of view.
Not only, however, did it take over 4,000 men nearly fifty days to make
twenty-two miles of line, but the work had been done in such a way that
when the autumn rains came on the track settled in many places; traffic
on the lines became very dangerous; one of the bridges was washed away
by the floods, and almost as many men had to be put on to do repairs as
had previously been employed for the construction. Traffic of a very
moderate description--each locomotive drawing only four wagons at a
time--was carried on for just twenty-six days, and then, happily for the
engineers concerned, the developments in and around Metz rendered the
line no longer necessary.
How the restoration of the traffic interrupted through the explosion of
French mines in the tunnel at Nanteuil occupied from September 17 to
November 22 has already been told on page 128.
RUSSO-TURKISH WAR
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account