The Valuation of Public Service Corporation Property: Transactions of the American Society of Civil Engineers,; vol. LXXII, June, 1911, ASCE 1190Riggs, Henry Earle
General
The Valuation of Public Service Corporation Property: Transactions of the American Society of Civil Engineers,; vol. LXXII, June, 1911, ASCE 1190
For rate-making, it is evident that an appraisal based on earnings will
utterly fail of its purpose if made during the lean years immediately
following construction. If made some years later, when the property has
begun to pay, the risk and necessary financial loss of the lean years
should be remembered, as any one building a road in the future will
necessarily have the same problems to meet, together with the expenses
of interest, depreciation, loss from operation, etc., both during the
construction and the lean years following, all of which must properly be
considered a part of the real cost of constructing and developing a
property.
J. E. WILLOUGHBY, M. AM. SOC. C. E. (by letter).—The determination of
the cost of reproducing the property of any steam railway involves,
together with other items, an estimate of the present cost of:
_First._—The acquirement of the right of way, to the extent, in the
form, and on the location of that held in connection with the
railway to be reproduced;
_Second._—The construction thereon of the roadway, to the form and
dimensions, and of the materials which the roadway to be reproduced
exhibits; and
_Third._—The seasoning and adaptation of the roadway to the state of
perfection which the roadway to be reproduced exhibits at the time
the estimate of cost of reproduction is made.
The first conception, for fixing the cost of the several items, is to
consider the railway to be reproduced as being non-existent at the time
the estimate is made, but having the environment which then exists along
the operated railway, although that environment may be largely of the
railway's own creating. The cost of the right of way is to be fixed as
ungraded and unimproved property attached and forming a part of the
adjoining improved property, which adjoining property will be entitled
to receive, in addition to the market value of the land taken, all
consequential damages due to the taking off of the right of way in the
form and location that the land has actually been taken, and for the
purpose of railway construction and operation. This adjoining property
is to give credit on the consequential damages for the incidental
benefits which it derives, if any, from the construction and operation
of the railway.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account