Little was done in 1881, but the work was divided into five sections,
and in the following year dredging and excavating were commenced. But,
even thus early, it was found to be more difficult than had been
expected. Up to March, 1883, only 659,703 metres had been excavated,
which was reckoned to be about 1/130th of the whole. This would not do,
as it meant that over a century would pass before its completion. About
seven thousand labourers, mostly Jamaica negroes, were employed at that
time, and this number was increased until, in 1888, there were 11,500.
In 1884 the average amount excavated was 600,000 metres per month,
against Lesseps' estimate of two millions. Yet, with all that, it was
calculated that in this year only 1/180th of the material had been taken
out.
The difficulties were enormous. First, there was trouble to find dumping
places, where the earth would not be again washed into the excavations
by heavy floods. Then came the rank vegetation, which was continually
stretching from either side to choke the clearing. Weeds grew six to
eight feet high in a rainy season, and these, with the straggling vines,
kept a little army at work to clear them away from the embankments and
tracks. The workmen suffered greatly from yellow and other fevers, and
£600,000 was spent on hospitals and their appurtenances. Money was spent
profusely on such things as grand offices and a magnificent house to
lodge the President, if he should ever come to inspect the works. All
along the route were ornamental bungalows, and the director-general at
Panama had a salary of £20,000, besides a house and other allowances.
Even he suffered from fever, and his wife and daughter died of it.
Up to 1888 about fifty millions sterling had been spent, and hardly a
fifth of the work was finished. Then financial difficulties led to an
arrangement for merging it in a new Company, which proposed to complete
the canal on a new plan. Notwithstanding all the objections to locks, it
was now proposed to save such an immense work of excavation by erecting
four on either side, thus bringing the highest water level to 123 feet.
Eighteen and a half miles were said to have been completed, of which
five were on the Pacific side and the remainder on the Gulf. To carry
out the new plan, £36,000,000 more were required, but, as a matter of
fact, only a third of the work necessary for this revised scheme had
been done.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account