The Installation of the undercrossing structure was handled by the
Southern Pacific Railway Company. The grading was handled by the County
grading forces under the supervision of the Highway Department. Mr. F.
H. Walker acted as resident engineer. The grading was commenced on
January 7, 1918, and completed August 1, 1918. The total cost of the
grading was $9,768.88, and was paid entirely from State funds.
COST STATEMENT ASHLAND HILL GRADING
Industrial insurance $ 156.27
Grading, labor, teams, material, etc. 8,928.19
Explosives 102.08
Concrete drainage structures 14.70
Pipe culverts 287.03
Irrigation flume diversions 5.40
---------
Total $ 9,493.67
Engineering 275.21
---------
Total cost $ 9,768.88
Ashland Hill Paving
Bids were called for on August 6, 1918, for the paving of the Ashland
Hill Section, but as no satisfactory bids were received the work was
undertaken by the Highway Department with State forces. This section of
paving is 4,200 feet in length, and the type of pavement laid is a
16-foot concrete, 5½ inches thick at the sides and 6½ inches thick at
the center. The mixture was a 1:2:3½, and a ratio of 5.6 gallons of
water per sack of cement was used.
The average haul on material was 1.2 miles and hauling was done by means
of trucks. The cement was shipped to the job prior to the beginning of
construction and stored at convenient locations near the work.
A sixteen cubic foot Koehring mixer equipped with boom and bucket was
used for mixing the aggregate. The pavement, after being struck off, was
finished by the roller and belt method. The pavement first being rolled
from two to four times depending on the condition of the concrete and
later belted with eight and ten inch belts. The eight inch belt being
used first. A very satisfactory surface was obtained in this manner.
[Illustration: CONCRETE PAVEMENT ON ASHLAND HILL IN JACKSON COUNTY, ON
THE PACIFIC HIGHWAY NORTH OF ASHLAND. GRADED AND PAVED IN 1918]
Continuous forms were used on this work and ¼x4 inch elastite joints
were placed at 30 foot intervals, leaving approximately two inches of
concrete above the elastite and giving the pavement the appearance of
monolithic construction. It was found that a better riding pavement
could be produced in this way as the inequalities at joints were
eliminated and we believe that the use of this pavement will justify the
adoption of this type on future work.
Gravel and crushed rock shoulders two feet wide were built on this
section and the pavement was not covered while curing as the weather was
cool and damp. However, the pavement was kept wet by sprinkling when
necessary.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account