To provide for the river navigation, the U. S. Engineers required a
minimum horizontal clearance normal to the channel of 120 feet and a
vertical clearance of at least sixty-six feet above low water, in case a
high level type of bridge were adopted. After careful study it was
decided to construct a high level bridge of the deck type, and to carry
the pony channel span on cantilevers projecting from the adjoining
spans, giving an arch effect over the channel. By this type of
construction, a clear distance of about 145 feet between channel piers
was obtained.
To minimize the cost of fabrication and erection of steel, four spans
were made practically the same. The east span was necessarily shorter
than the typical ones, since otherwise it would place the channel
opening too far across the river. This span is not so deep as the
adjoining one, and the difference in height is made up by means of a
rocker under the small span, which, of course, also serves the purpose
of movable shoes. The channel span rests on cast steel rockers on one
end, which are carried by a shelf on the cantilever panel. The opposite
end of the span was pin connected.
Previous to the design of the bridge, wash borings were made, which
indicated in a general way that the bed of the stream was composed of a
few feet of gravel, underlaid with sand for a considerable depth. It was
accordingly decided to carry the foundations down below the probable
point of future scour, and carry the loads entirely upon piling. The two
channel piers were sunk about thirty-five feet below low water.
The west approach is carried on fir piling treated in an open vat with
carbolineum to a temperature of about 220 degrees F.
Lumber being comparatively cheap, the entire roadway deck of the bridge
and wooden approach is composed of fir, three by seven inches and
twenty-six feet long on edge, spiked together, thus projecting a foot
outside the curb on either side, the roadway being twenty-four feet
between curbs. An asphaltic wearing surface three and one-half inches
thick effectively waterproofs the wood, and the small interstices
between the pieces will allow sufficient circulation of air to preclude
any possibility of attack of dry rot. The ends of the floor members were
painted with hot carbolineum, as were also the wooden members contiguous
to openings in the floor occasioned by expansion joints between spans.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account