During 1918 Morrow County graded 2.26 miles of standard road adjacent to
the town of Heppner. A 1.82-mile section begins at the west city limits
of Heppner and extends down Willow Creek on the State survey. Another
section extends from the east city limits up Hinton Creek for a distance
of .44 miles.
The County paid the total cost of this improvement which required
$5,689.19. The State Department supplied the engineering supervision for
this work through R. H. Baldock, resident engineer.
Following is a statement of construction quantities:
HEPPNER EAST
Common Excavation, 1,190 cu. yds. at. 43 $502.53
Culverts 216.35
-------
Total $ 718.88
HEPPNER WEST
Common Excavation, 850 cu. yds. at .48 $ 407.01
Intermediate Excavation, 2,150 cu. yds. at $1.11 2,385.30
Culverts 2,178.00
---------
Total $ 4,970.31
Jones Hill Grading
The 3.22-mile section of the Oregon-Washington Highway known as the
Jones Hill Grade, lies about ten miles east of Heppner, and extends over
the divide between Hinton and Butler Creeks. The State location involved
the construction of an entirely new road. This improvement was paid for
in full by the County, the total cost being $25,050.26.
R. H. Baldock, resident engineer for the State Highway Department, was
the engineer in charge.
Construction quantities are shown in the following statement:
Rock Excavation, 6,200 cu. yds. at $3.98 $ 18,504.26
Common Excavation, 7,300 cu. yds. at .59 4,350.00
Culverts 2,200.00
----------
Total cost $ 25,054.26
Heppner Macadam
After grading the 1.82-mile section of the Oregon-Washington Highway
west of Heppner, and .44 miles east, Morrow County proceeded to surface
with a standard waterbound macadam. This work was done on a force
account basis by the United Contracting Co. and Warren Construction Co.
The work was completed and opened to traffic in July, 1918.
The 2.26 miles of macadam cost the County a total of $19,280.35. A total
of 4,208 cubic yards of rock was placed, making the unit cost $4.56 per
cubic yard. Crushed trap rock was secured from a quarry near the city
limits, and suitable binder material was found near at hand. The
engineer in charge was R. H. Baldock of the State Department.
MULTNOMAH COUNTY
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account