Third biennial report of the Oregon State Highway Commission : $b covering the period December 1st, 1916 to November 30th, 1918
Benson, Simon
Highway engineering -- Oregon -- History; Water resources development -- Systems engineering -- Oregon -- History
Engineering $6,391.47
Contract Construction Work as follows--
Common Excavation, 10,835.3 Cu. Yds. at 60c $6,501.18
Intermediate Excavation, 1,959.5 Cu. Yds. at
90c 1,763.55
Overhaul, per 100 Lin. ft., 6,314.8 Cu. Yds.
at 2c 126.30
12-inch Reinf. Conc. Pipe (Placing only) 84
Lin. ft. at 48c 40.32
18-inch Reinf. Conc. Pipe (Placing only) 607
Lin. ft. at 78c 473.46
24-inch Reinf. Conc. Pipe (Placing only) 384
Lin. ft. at $1.16 445.44
36-inch Reinf. Conc. Pipe (Placing only) 64
Lin. ft. at $1.80 115.20
Clearing and Grubbing (Force Account) 543.75
Moving Fences (Force Account) 4.00
Standard Bitulithic Pavement, 47,555.5 Sq. Yds.
at $1.42 67,528.81
Broken Stone Loose measure, 8,840 Cu. Yds. at
$2.20 19,448.00
Crushed Stone Shoulders, 7,466 Lin. ft. at 6c 447.96
----------
Total Amount Earned by Contractors to Nov. 30,
1918 97,437.97
Less 15% retained pending completion 14,615.69
----------
Total Payments to Contractor to November 30, 1918 82,822.28
----------
Total Expenditure to November 30, 1918 89,213.75
Paid by State 63,203.90
Paid by County 26,009.85
----------
Total $89,213.75
Three Rivers Forest Project
A Federal Aid Forest Road Project is now under construction between Hebo
and Dolph in Tillamook County. This project is 10.3 miles in length,
includes grading and nine foot rock surfacing, and is estimated to cost
$122,000.00 of which $21,500.00 will be paid by the County, $50,250.00
by the State, and $50,250.00 by the Federal Government.
This work is handled under the supervision of Federal Office of Public
Roads. The contract was awarded to the Tillamook County Court, but the
State's Attorney General ruled that the Court had no authority which
would allow them to contract to do work of this nature. To facilitate
matters the Highway Commission took the contract over from the County,
and the work is now in progress, the Highway Department acting as
contractors and being paid for the work at the unit prices originally
bid by Tillamook County.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account