An effort has been made to secure Federal Aid in the construction of a
section of the Portland-Tillamook Highway from Grande Ronde west. With
this in view, the necessary surveys have been made, and it is expected
that Federal Aid will be secured so that the construction may be
undertaken during the 1919 season.
Sheridan Paving--1917
In 1917 the Highway Department constructed with its own forces and
equipment 1.8 miles of concrete pavement from Sheridan east on the
Sheridan-McMinnville Road. This pavement was 16 feet wide, 6½ inches
thick at the center and 5½ inches thick at the edges. The mix used was a
1:1½:3.
In connection with the paving there was a considerable amount of
grading, the total expenditure for grading, culverts, etc., being
$5,651.70. The cost of the 1.8 miles of paving was $31,432.99, the unit
cost being $1.82 per cubic yard.
Yamhill County co-operated in the payment for this work to the amount of
$10,000.00. A complete statement of the costs on this work is given
below.
COST STATEMENT--SHERIDAN PAVING--1917
Quantity Item Cost Unit Cost
2498 cu. yds. Common Excavation }
652 cu. yds. Intermediate Excavation } $ 4,442.85 $ .906
1750 cu. yds. Solid Rock Excavation }
182 lin. ft. 12-inch Culvert Pipe 283.90 1.56
118 lin. ft. 18-inch Culvert Pipe 276.00 2.34
44 lin. ft. 24-inch Culvert Pipe 134.20 3.05
290 lin. ft. 6-inch Porous Drain Tile 52.25 .18
25 cu. yds. Class "C" Concrete 462.50 18.50
17,150 sq. yds. Concrete Pavement 31,198.87 1.82
5050 lin. ft. Expansion Joints 234.12 .046
-----------
Total Construction Cost $ 37,084.69
Engineering 1,131.35
-----------
Grand Total Cost $ 38,216.04
Paid by State $ 28,216.04
Paid by County 10,000.00
-----------
Total $ 38,216.04
Sheridan Paving--1918
Early in 1918, Yamhill County requested that the concrete pavement laid
in 1917 be continued to a total length of four miles, and offered to pay
for all grading necessary in connection therewith. This request was
granted by the Highway Commission and in the early spring, construction
was started on the additional 2.2 miles.
The type of pavement laid on this section was the same as that laid in
1917, except that crushed rock aggregate was used instead of gravel, and
the mix was reduced to 1:2:3½.
[Illustration: STATE OWNED PAVING PLANT IN OPERATION NEAR SHERIDAN IN
YAMHILL COUNTY. ON THE YAMHILL NESTUCCA HIGHWAY]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account