The room for noting time of set and soundness is fitted with a mixing
table similar to that in the briquette-making room. The Vicat apparatus
is used for determining the normal consistency, and the Gilmore
apparatus for the time of setting. While setting, the soundness pats are
stored in galvanized-iron pans having about 1 in. of water in the
bottom, and covered with dampened felt or burlap. The pats rest on a
rack slightly above the water and well below the felt.
For specific gravity tests, the Le Chatelier bottles are used. A pan, in
which five bottles can be immersed at one time, is used for maintaining
the benzine at a constant temperature. The samples are weighed on a pair
of Troemner’s No. 7 scales.
The fineness room is fitted with tables, two sets of standard No. 100
and No. 200 sieves, and two Troemner’s No. 7 scales similar to those
used for the specific gravity tests.
The storage room is fitted with shelves for the storage of samples being
held for 28-day tests.
The mould-cleaning room contains tables for cleaning moulds, and racks
for air pats.
An effort is made to keep all the rooms at a temperature of 70° Fahr.,
and, with this in view, a Bristol recording thermometer is placed in the
briquette-room. Two wet-and-dry bulb hygrometers are used to determine
the moisture in the air.
Samples are taken from the conveyor which carries the cement to the
storage bins, at the approximate rate of one sample for each 100 bbl.
After each 4,000-bbl. bin has been filled, it is sealed until all tests
have been made, when, if these have been satisfactory, it is released
for shipment.
The samples are taken in cans, 9 in. high and 7½ in. in diameter. These
cans are delivered in the preparation room where the contents are mixed
and passed through a No. 20 sieve. Separate samples are then weighed out
for mortar briquettes, for soundness pats, and for the specific-gravity
and fineness tests. These are placed in smaller cans and a quantity
sufficient for a re-test is held in the storage room awaiting the
results of all the tests.
The sample for briquettes is mixed with three parts standard crushed
quartz, and then taken to the briquette-making room, where eight
briquettes are made, four for 7-day and four for 28-day tests. These are
placed in the moist closet in damp air for 24 hours, then removed from
the moulds, and placed in water for the remainder of the test period. At
the proper time they are taken from the immersion tank and broken.
From the sample for soundness, four pats are made. The time of setting
is determined on one of these pats. They are placed in the pan
previously described, for 24 hours, then one is placed in running water
and one in air for 28 days. The others are treated in the boiler, one in
boiling water for 3 hours and one in steam at atmospheric pressure for 5
hours.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account