The following extract from the Adams Transcript, for April 11, 1872,
gives a summary of the progress made during the month of March, and the
lengths remaining to be opened to complete the work:
[Illustration: Profile of the Hoosac Mountain, and Advance of Tunnel,
January 1, 1872.]
HOOSAC TUNNEL PROGRESS FOR MARCH, 1872.
“East End, 120 feet; Central Shaft, eastward, 100 feet; West End, 140
feet, total, 360 feet. Total lengths opened to April 1, 1862: East End,
10,166 feet; Central Shaft, east, 617 feet, west, 325 feet, total, 942
feet; West End, 7,494 feet. Lengths remaining to be opened: between
East End and Central Shaft, 2,054 feet—586 feet less than half a mile.
Between West End and Central Shaft, 4,375 feet—855 feet more than
two-thirds of a mile.”
A reference to the wood cut opposite page 80, shows the profile of the
mountain and progress of the Tunnel to January 1, 1872.
The distance made during the month of March, in the East heading, was
120 feet of heading, 24 feet wide and 9 feet in height, exclusive of
first enlargement or roof, and second enlargement of roof to full
size or stopeing, which is usually carried on simultaneously to about
250 feet per month. This heading is being attacked by twelve of the
Burleigh drilling machines, mounted on two carriages manned by eight
miners and a foreman, who work for eight hours, with brief intermission
whilst the charges are being fired. The drills are impelled by
compressed air, making 300 strokes per minute, and calculated to strike
with a force of 200 lbs. at each blow, perforating from one inch to
five inches per minute, of a hole two inches in diameter when powder
is used, and 1½ inch diameter for Nitro-Glycerin blasting. At the East
heading, partly owing to the rock being softer than either at the West
End or in the Central Shaft, partly to the miners being accustomed to
powder, partly to the heavy battery of drills enabling twelve drilling
machines to work at once, and thus make progress satisfactory to the
contractors, who, wisely, let well enough alone, the holes when drilled
to a depth of from two feet six inches to three feet, are each charged
with from one to two and one-half pounds of blasting powder, then
tamped; the carriages are drawn back, and the sixteen to twenty-six
holes are fired simultaneously by means of a frictional electric
machine. This takes place every four hours, exploding from 100 to 150
cartridges every twenty-four hours. The reader must not infer from
this that every blast makes from two feet six inches to three feet
of advance; because, first, the holes are never drilled for powder
in a horizontal plane, but at an angle, sometimes upwards, sometimes
downwards, to the right or left, the aim being, that a straight line
drawn from the bottom of the hole to the face of the rock shall be
shorter than the extreme length of the drilled hole, so that the charge
or blast which exerts its force in the line of least resistance, may
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account