=Conditions of Work.=--The construction of tunnels under city streets
may be divided into two classes, which may be briefly defined as shallow
tunnels and deep tunnels. Shallow tunnels, or those constructed at a
small depth beneath the surface, are usually built by one of the
cut-and-cover methods; deep tunnels, or those built at a great depth,
beneath the surface are constructed by any of the various methods of
tunneling described in this book, the choice of the method depending
upon the character of the material penetrated, and the local conditions.
In building tunnels under city streets the first duty of the engineer is
to disturb as little as possible the various existing structures and the
activities for which these structures and the street are designed. The
character of the difficulties encountered in performing this duty will
depend upon the depth at which the tunnel is driven. In constructing
shallow tunnels by the cut-and-cover method care has to be taken first
of all not to disturb the street traffic any more than is absolutely
necessary. This condition precludes the single trench method of open cut
tunneling in all places where the street traffic is at all dense, and
compels the engineer to use the methods employed in Paris and New York,
as previously described, or else the transverse trench or slice method
employed in the Boston Subway.
These methods have to be modified when the work is done on streets
having underground trolley and cable roads, and in which are located gas
and water pipes, conduits for wires, etc. Where underground trolley or
cable railways are encountered, a common mode of procedure is to
excavate parallel side trenches for the side walls, and turn the roof
arch until it reaches the conduit carrying the cables or wires. The
earth is then removed from beneath the conduit structure in small
sections, and the arch completed as each section is opened. As fast as
the arch is completed the conduit structure is supported on it. Where
pipes are encountered they may be supported by means of chains,
suspending them from heavy cross-beams, or by means of strutting, or
they may be removed and rebuilt at a new level. Generally the conditions
require a different solution of this problem at different points.
Another serious difficulty of tunneling under city streets arises from
the danger of disturbing the foundations of the adjacent buildings. This
danger exists only where the depth of the tunnel excavation extends
below the depth of the building foundations, and where the material
penetrated is soft ground. Where the tunnel penetrates rock there is no
danger of disturbing the building foundations. To prevent trouble of
this character requires simply that the excavation of the tunnel be so
conducted that there is no inflow of the surrounding material, which
may, by causing a settlement of the neighboring material, allow the
foundations resting on it to sink.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account