Weehawken side was done in the bare rock excavation where timber
falsework was used. After the shields were finished and in position, the
first two rings of the lining were erected in the tail of the shield.
These rings were firmly braced to the rock and the chamber lining; then
the shields were shoved ahead by their own jacks, another ring was built
and so on.
[13] Condensed from paper by James Forgie, “Eng. News,” Vol. LVI, and
by H. B. Hewett and W. L. Brown, “Proc. Am. Soc. C. E.”, Vol. XXXVI.
[Illustration: ~Rear Elevation of Shield.~
~Vertical Section.~
~Half Section A-B.~
~Half Section C-D.~
~Horizontal Section.~
FIG. 138.--General Elevations and Sections of Shield.]
=Shield.=--The shields used in these tunnels were designed by Mr. James
Forgie, M. Inst. C. E. and M. Am. Soc. C. E., and were provided with
three innovations: the segmental doors, the sliding platforms and the
removable hood. The shields, Fig. 138, were circular, 23 ft. 6¹⁄₄ ins.
in external diameter, and were 16 ft. long, exclusive of the hood. The
tail of the shield overlapped the lining, the maximum being 6 ft. 4¹⁄₂
ins. during ordinary working; the minimum, 2 ft. during the operation of
taking any ram out for repairing. The shields had only one transverse
bulkhead made up of two continuous horizontal platforms and three
vertical partitions stiffening angular web plates fore and aft the ram
chambers. They were connected by angles and skin plates which formed a
ring-shaped frame 25 ins. thick radially and nearly 5 ft. long. Between
the vertical and horizontal partitions were left openings which either
were partially or entirely closed by segmental doors pivoted on an axis
parallel to the face of the shield bulkhead. There were nine of such
openings on each shield, the clear width being 2 ft. 7 ins., the height
varying from 2 ft. 2 ins. to 3 ft. 4 ins., according to the location.
The hood at the front of the shield was designed so as to be detached
underground and was made of complete segments to permit easy erection or
detachment. The hood was extended as far as the upper platform, thus
protecting only the roof of the excavation. It was attached to the
shield by means of bolts, and, when removed, it was replaced by the
cast-steel cutting-edge, built in 24 sections and placed all around the
shield. The eight sliding platforms, another characteristic of this
shield, could be extended 2 ft. 9 ins. in front of the shield by means
of hydraulic rams, and, when so extended, were able to stand a pressure
of 7900 lbs. per sq. ft. These sliding platforms were used as hoods for
the protection of the men working through loose soils, while in rock
they enabled the drilling and blasting to be carried on at three levels.
A water trap or bird fountain was constructed, at the rear of the
bulkhead of the shield, by means of angle irons to which steel plates
were bolted. The opening to the face was so spacious that in an
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account