_Setting Up Centers._--According to the method of excavation followed in
building the tunnel, the centers for building the roof arch may have to
be supported by posts resting on the tunnel floor; or where the arch is
built first, as in the Belgian and Italian methods, they may be carried
on blocking resting on the unexcavated earth below. Whichever method is
employed, an unyielding support is essential, and care must be taken
that the centers are erected and maintained in a plane normal to the
tunnel axis. To prevent deflection and twisting, the consecutive centers
are usually braced together by longitudinal struts or by braces running
to the adjacent strutting. Only skilled and experienced workmen should
be employed in erecting the centers; and they should work under the
immediate direction of the engineer, who must establish the axis and
level of each center by transit and level.
_Lagging._--By the lagging is meant the covering of narrow longitudinal
boards resting upon the upper curved chords of the centers, and spanning
the opening between consecutive centers. This lagging forms the curved
surface or mold upon which the arch masonry is laid. When the roof arch
is of ashlar masonry the strips of lagging are seldom placed nearer
together than the joints of the consecutive ring stones, but in brick
arches they are laid close together. Besides the weight of the arch
masonry, the lagging timbers support the short props which keep the
poling-boards in place after the strutting is removed and until the arch
masonry is completed.
_Striking the Centers._--The centers are usually brought to the proper
elevation by means of wooden wedges inserted between the sill of the
center and its support, or between the bottom of the posts carrying the
center and the tunnel floor. These wedges are usually made of hard wood,
and are about 6 ins. wide by 4 ins. thick by 18 ins. long. To strike the
center after the arch masonry is completed, these wedges are withdrawn,
thus allowing the center to fall clear of the masonry. Usually the
center is not removed immediately after striking, so that if the arch
masonry fails the ruins will remain upon the center. The method of
striking the iron center devised by Mr. Rziha has been described in the
previous chapter on strutting.
CHAPTER VIII.
METHODS OF LINING TUNNELS.
Tunnels in soft soils and in loose rock, and rock liable to
disintegration, are always provided with a lining to hold the walls and
roof in place. This lining may cover the entire sectional profile of the
tunnel, or only a part of it, and it may be constructed of timber, iron,
iron and masonry, or, more commonly, of masonry alone.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account