=Method of Excavation.=--The work at each end of the tunnel is carried
on quite independently, consequently, though similar in principle, the
methods vary in detail, apart from the fact that different geological
strata require different treatment. Broadly speaking, the two parallel
headings, each 59 sq. ft. in section, are first driven by means of
drilling-machines and the use of dynamite, this work being carried on
day and night, seven days in the week; No. 1 heading is then enlarged to
full size by hand-drilling and dynamite. On the Italian side, where the
rock is hard and compact, breakups are made at intervals of 50 yds., and
a top gallery is driven in both directions, but, for ventilation
reasons, is never allowed to get more than 4 yds. ahead of the break-up,
which is gradually lengthened and widened to the required section. No
timbering is required, except to facilitate the excavation and the
construction of the side walls. Steel centers are employed for the arch;
they entail fewer supports, give more room, and are capable of being
used over again more frequently without damage. They consist of two
I-beams bent to a template and riveted together at the crown, resting at
either side on scaffolding at intervals of 6 ft.; longitudinals 12 ft.
by 4 ins. by 4 ins. support the roof. Hand rock-drilling is carried out
in the ordinary way, one man holding the tool and a second striking;
measurements of excavation are taken every 2 or 3 yds., a plumb-line is
suspended from the center of the roof, and at every half-meter (20 ins.)
of height horizontal measurements are taken to each side.
At the Brigue end a softer rock is encountered, necessitating at times
heavy timbering in the heading, and especially in the final excavation
to full size, Fig. 56. The bottom heading, 6 ft. 6 in. high, is driven
in the center, and the heading is then widened to the full extent and
timbered; the concrete forming the water channel and the foundation for
one side wall is put in; the side walls are built to a height of 6 ft. 6
ins., and the tunnel is fully excavated to a further height of 6 ft. 6
ins. from the first staging. The side walls are then continued up for
the second 6 ft. 6 ins., and from the second floor a third height of 6
ft. 6 ins. is excavated and timbered. Finally the crown is cleared out,
heavy wooden centers are put in, the arch is turned and all timbers are
withdrawn except the top poling-boards, supporting the loose rock.
[Illustration: FIG. 56.--Sketches Showing Sequence of Work in Excavating
and Lining the Simplon Tunnel.
1
2
3
4
5
6
7
8]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account