An OY strip had been completed on 13 November at Koto-ri, but heavier
engineer equipment was needed at Hagaru. Before it could be brought
forward, the road from Chinhung-ni to Koto-ri required strengthening
and widening. This task had already been assigned to Lieutenant Colonel
Partridge, commanding the 1st Engineer Battalion. After a survey by
jeep, he decided to begin operations at the highest point of the
one-way dirt road.
“By working down,” he explained, “we could first of all provide for
what we considered to be a dangerous accumulation of snow, and the
problem of land slides.... The work on the road involved a good bit
of drainage in order to insure that the melting snows from day to day
during the sunlight hours would not filter across and destroy the road
bed. It involved demolitions and drilling and a good deal of dozer and
grader work.”[335]
[335] LtCol J. H. Partridge interv by HistDiv, HQMC, 25 Jun 51,
31–32.
Enough progress had been made by 18 November so that armor could be
sent forward to support RCT-7. Only the day before, the 1st Tank
Battalion had begun functioning with its Headquarters and Service
Companies at Soyang-ni, eight miles northwest of Hamhung. The road
between Chinhung-ni and Koto-ri was still impassable for M-26
(Pershing) tanks until the engineers could widen some of the turns. But
Lieutenant Colonel Harry T. Milne, the battalion commander, organized
a provisional tank platoon consisting of two M4A3 (Sherman) tanks from
Headquarters Company and four dozer tanks from Company D at Majon-dong.
They proceeded without incident on the 18th to Hagaru, operating as a
gun platoon.[336]
[336] 1stTkBn _SAR_, 18. 1stEngrBn had been ordered to prepare
the MSR for tank use on 6 Nov. CG 1stMarDiv msg to CO
1stEngrBn, 1530 6 Nov 50.
Opening the mountain road to heavy traffic made it possible on the
18th to begin work on the Hagaru airstrip. Five large dozers with pans
of eight cubic yards capacity arrived at the site the next day, and
Company D of the 1st Engineer Battalion tackled the job of hacking out
a runway from ground frozen as hard as granite. Plans called for a cut
of 90,000 cubic yards and a fill of 60,000 for a 3200-foot runway. The
rub was that engineering field manuals prescribed a runway of 3600 feet
for R4Ds or C-47s at sea level, plus an additional 1000 feet for each
1000 feet of altitude. And since Hagaru was about 4000 feet above sea
level, it could only be hoped that pilots were right in estimating that
a strip of 3000 to 4500 feet might do in a pinch.[337]
[337] CG 1stMarDiv msg to CG X Corps, 1229 18 Nov 50; Partridge
interv, 25 Jun 51, 39–40.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account