Up to February 1883 the work undertaken at the canal had been almost
entirely preliminary. In that month M. de Lesseps, acting upon
recommendations contained in a report made by M. Dingler, chief
engineer of roads and bridges, proposed to the shareholders of the
company that the definite programme of the work to be done should
embrace a canal of a depth of nine metres below sea level, and a width
of 22 metres throughout its course; the construction of large ports at
Colon and at Panama; a great basin, five kilometres in extent, near
Tavernilla, about the centre of the canal, in order to allow vessels
to pass each other; a great dam at Gamboa, for the regulation of the
course of the Chagres river; and a tidal port at Panama, in order to
ensure access to and from the Pacific at all hours. In submitting this
programme, M. de Lesseps calculated that the excavation necessary to
the completion of such a canal would be about 110 millions of cubic
metres, and that the work of regulating the Chagres river would be
equal to a further 10 millions of cubic metres. This work, M. de
Lesseps estimated, could be completed in 1888—the excavations of land
in three years, and the dredging operations in two, so that “the canal
could, with mathematical certainty, be opened on the 1st January 1888.”
In confirmation of this calculation, he appealed to the experience at
Suez, where, with a total of 75 millions of cubic metres of excavation,
50 millions were done during the two last years of the work.
The state of affairs at the canal in the autumn of 1884 is described by
the American Admiral Cooper, who reported that although comparatively
little had been done in the actual work of excavation, in relation to
the vast work to be accomplished, yet all the preliminary plans had
been prepared, the soundings had been made, the line of route had been
cleared of its tropical vegetation, large supplies of materials of
all kinds were at command, dwellings and barracks for the employés
had been erected in elevated and salubrious localities, hospitals
had been established, and every arrangement requisite for meeting
possible eventualities had been carried out so completely that he was
confirmed in the belief that the canal would be finished in due time,
although he doubted its completion in 1888. At this time no less than
twenty different contractors, of eight different nationalities, were
engaged upon the work of construction. These contractors had undertaken
collectively to raise 62,691,000 cubic metres of excavation for a sum
total of 219,295,000 francs (8,772,000_l._ sterling), being at the rate
of rather less than 3_s._ per cubic metre. As the total quantity of
excavation required was estimated at 120 millions of cubic metres, the
opinion was held that the mere work of clearing the course of the canal
could be accomplished for about 440 millions of francs, or rather less
than 18 millions sterling.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account