Waterways and Water Transport in Different Countries: With a description of the Panama, Suez, Manchester, Nicaraguan, and other canals.
Jeans, J. Stephen (James Stephen)
Canals
These things being so, two results not unnaturally follow—the first,
that it was difficult to get the highest class of labour to undertake
the work; and the second, that the rate of wages paid, and the cost
of the work generally, were exceptionally high. During the years
1884-85-86, the _personnel_ on the canal ranged between 12,000 and
25,000; and although M. de Lesseps announced in 1885 that the Company
had undertaken to provide barrack accommodation for 30,000, it is
doubtful whether that number was ever employed on the works at any one
time. We have already seen that the first contracts made with a number
of different contractors provided for the cost of excavation being
brought under 3_s._ per cubic metre. Señor Armero, however, in a report
made on the progress of the work in the latter part of 1887, stated
that every cubic foot had cost at least 2 dollars, or 8_s._ 4_d._ for
excavation, being nearly three times the amount at which M. de Lesseps
stated the first contracts to have been placed, for something like
one-half of the entire work.
With calculations so entirely falsified by results, the Panama Canal
Company found it necessary in 1887 to procure fresh capital. They
thereupon offered half a million shares, of the nominal value of 500
million francs at 440 francs on 1000 francs, and succeeded in raising
a further sum of about 114 million francs, making the total amount
of cash received to that date rather over 1001 million francs, or,
in other words, within 200 millions of the total amount for which
the canal was to have been completed. How far the canal still was
from completion at this time we may learn from the report made to
the Colombian Government in November 1887 by Señor Armero, who says
that the total amount excavated up to August of that year was about
34 millions of cubic metres, out of a total of 161 millions; that the
upper and easier part of the work had been accomplished, and that
greater difficulties would be encountered in working as the tide-level
was approached; that the cost of controlling the water of the Chagres
alone would amount to 471 million francs, or, roughly, one-third of the
whole estimated cost of the enterprise; that the sum still required to
complete the canal would be 3012½ millions of francs, or 120 millions
sterling, being nearly three times as much as the whole original
estimated cost; and that the amount to be paid on capital loaned during
the next six or seven years would add perhaps 40 millions sterling to
this amount.
This unfavourable report had naturally a depressing effect upon the
scheme when it was made public. And yet the reporter was not entirely
unfavourable to the enterprise. On the contrary, he prefaced his report
by the following remarks:—
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account