Perhaps one of the most anxious tasks which falls to the lot of an
engineer is the renewal of under-line bridges and viaducts on a
working line. On a new line in course of construction the entire site 158
of the work is at the disposal of the erectors, and the building of a
bridge or viaduct can be carried on with a freedom which cannot be
obtained on an open line. On a working railway, the train service must
be kept going, irrespective of renewals, and very often the best that
can be done is to reduce the double line to single line working at the
site of the operations. It is not always expedient or possible to make
a temporary bridge and diverted line for traffic purposes, as the
expenditure to be incurred might be too great to warrant the outlay,
or there may be local difficulties to effectually prevent the
introduction of a provisional structure. The taking down of one half
of the old structure may necessitate the removal of stays and bracing
affecting the stability of the half remaining to carry the traffic,
and thus render temporary shoring and bracing necessary. The erection
of the new work in such a limited space has to be watched with great
care; all cranes, lifting appliances, and scaffolding must be kept
clear of vehicles moving over the running-line, and very frequently it
is found prudent to cease erecting operations during the passage of a
train.
In very many cases of renewals, the description and arrangement of the
old structure will materially influence or control the design for the
new one, and the details of the latter must be schemed out so as to
disturb as little as possible the stability of the old work remaining
as the working road.
The following list gives the lengths of the main spans of some railway
bridges, and may be found useful for reference:--
LENGTHS OF MAIN SPANS OF SOME LARGE RAILWAY BRIDGES.