=Sizes of Stone.=--The stone for the wearing course of a macadam road
should be as large as practicable, because the larger the pieces the
more durable the surface. If the individual stones are too large it is
difficult to secure a smooth surface, and large stones will be readily
loosened by tipping as the wheels roll over them. These considerations
limit the size to a maximum of that which will pass a 2-1/2-inch
screen. Stone of excellent wearing qualities may be somewhat smaller,
but never less than that which will just pass a 1-1/2-inch screen.
For the lower course, the size is not particularly important except
where the earth foundation is such as to require special construction.
It is not uncommon to use the same size of stone for both upper and
lower course and yet in many instances stone up to that which will
just pass a 3-1/2-inch screen is used for the lower course. Stone much
smaller in size may also be used successfully, but if the stone is
broken to a smaller size than is required, unnecessary expense is
incurred.
The bonding material is the finer portion of the product of the
crusher, which is called screenings. This material may be so finely
crushed as to pass a one-fourth inch screen, or may be so coarse as to
just pass a one-half inch screen, but in any case must contain all of
the dust and fine material produced by the crusher.
Where the soil and drainage conditions demand an especially stable
foundation course, the Telford type is used. The Telford foundation
consists of a layer of stones of various dimensions that can be laid
so as to give a thickness of 8 inches. These large stones are placed
by hand and therefore the size requirements are not rigid. Stones
having one dimension about 8 inches and the others not over 10 or 12
inches are satisfactory.
=Earth Work.=--A thoroughly drained and stable earth foundation is
essential to success with the macadam type of surface. Before placing
the stone, the road must be shaped to the proper cross section and
all grade reduction work completed. Preferably heavy fills should have
a year to settle before the macadam surface is placed. Side ditches,
necessary culverts and tile drains should be constructed as required
for drainage. The earth work is often carried out in connection with
the construction of the macadam surface, being completed just ahead of
the surfacing. In that case, the fills must be carefully rolled as
they are placed. The road bed may be shaped in connection with the
other earthwork. If the road has been brought to a satisfactory grade
some time prior to placing the macadam, the road bed for the broken
stone will be prepared as needed for placing the stone.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account