Specifications Nos. 3 and 4 are more or less included in specification
No. 2. Specification No. 5, however, is also of great importance.
Information that is stale is about as useless as no information at all.
If you tell a foreman on Monday that the work of his gang for the week
ending ten days before was not up to the mark, he will not have much
respect for your cost─keeping system; he will certainly not remember
sufficiently well the causes that produced his bad work, to remedy
them; or he will be able to pick out of the haze of history enough
excuses to let himself out of the responsibility of his bad work, and
to put his manager at sea as to where this foreman and his gang really
stand. It is therefore of prime importance that the arrangement for
showing the manager what his costs are, with the salient conditions
affecting such costs, shall be so rapid as to be "red─hot" all the
time.
The commonest arrangement of cost showing──and the only one ordinarily
found at the present day on most contract work──is an abstract prepared
on a piece of yellow paper by the time─keeper for the inspection of
the manager each morning; and this has so few disadvantages that it
would be very satisfactory, were it not that it is impossible from it
to compare at a glance the work done, let us say yesterday, with that
done previously. It is, however, far better than any other system which
lacks any of the essentials indicated above.
USE OF CHARTS
The best method that has so far been devised is by the use of charts
showing to scale the different unit─costs for the various days in the
month. Such charts are illustrated in Figs. 7 and 8. They are from the
records of the Construction Service Company. One of these (Fig. 7)
indicates the cost of channeling rock. It will be seen from the line
_A_, that during this month the number of square feet channeled varied
from 75 to 375, and that the labor cost varied from a maximum of 62
cents to a minimum of 8 cents. On the 8th, the morning crew did not
work, because, as it happened, of severe weather, which accounted for
the low output on that day. On the 24th, the night shift allowed the
pipes to freeze up. It may be mentioned that the foreman of the night
shift, whose name appears in brackets on the chart, has since turned
his attention to other fields of industry than channeling. On the 28th,
the channeler had reached a point where the cut was frequently filled
up by earth that slid in from the side and caused such a large amount
of sludge as to cushion the blows of the blade; and the chart shows on
that day a high cost, due to the cleaning away of this earth.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account