Demobilization : $b our industrial and military demobilization after the armistice, 1918-1920Crowell, Benedict
History
Demobilization : $b our industrial and military demobilization after the armistice, 1918-1920
Crowell, Benedict
United States. Army. American Expeditionary Forces -- Demobilization; World War, 1914-1918 -- United States
This system had nothing to do with the settlement of claims arising
out of the War Department’s operations in real estate during the war.
There were thousands of claims for damage done to property incidental
to the training of the Army. To settle such claims the Secretary of
War utilized the existing War Department Board of Appraisers, which
had been created to establish the values of commandeered property. The
commanders of military posts investigated the validity of real estate
claims and recommended awards. These, after approval by the Board of
Appraisers and the Secretary of War, were paid by the auditor of the
War Department. Numerous real estate claims arose under informal and
invalid agreements, and the condition of such claimants was usually
particularly helpless. When the War Department started to build its
great trinitrotoluol plant at Racine, Wisconsin, a large number
of persons, home owners and renters, moved off the site without
the formality of written contracts. Many of these individuals sold
their farm animals and household goods. The armistice cut short the
construction of the plant, and then the property owners discovered that
they were without legal standing before the Government. The Dent Law
enabled the Department to settle these and other real estate claims
arising under informal contracts, and the Board of Appraisers made the
settlements.
The Canadian contracts, both formal and informal, were adjusted by
the Imperial Munitions Board, acting in conjunction with two American
officers called assessors, one of whom was a special member of the War
Department Claims Board. Mr. D. C. Jackling, the director of United
States Government Explosives Plants, adjusted all the outstanding
contracts and orders in connection with the construction of the Nitro
(West Virginia) Powder Plant. More than 3,200 firms and individuals
had received orders for materials for the plant, and a fire at the
plant immediately after the armistice destroyed the records of all open
orders. The terms of these orders were reëstablished by correspondence
with the contractors. A special settlement board within the Ordnance
Department adjusted the terminated contracts for the construction
of nitrogen fixation plants authorized as a war measure. The Spruce
Production Corporation of the Air Service terminated and settled its
own contracts with the spruce lumber interests in the Northwest.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account