This method involves the expense of moving the temporary roads, but
allows more time for subsidence, and the mass of an embankment is not so
exposed to the weather; however, in a dry season, an embankment can
often be tipped to the full height, whereas in wet or changeable weather
it would not stand if so deposited, and two lifts may be required. Care
should be taken that the width is always sufficient to receive the top
lift. It is more in the direction of equally reducing the height the
material has to be tipped, especially in treacherous soils, that
solidity is to be attained, than in an attempt to consolidate earth by
endeavouring to cause it to fall together by deposition from two or more
separate parallel roads at the same level.
Many slips and failures of embankments have been caused by the central
portion being deposited of one material, such as clay, and the slopes
afterwards made of a different earth, as rock. The latter will then slip
upon the greasy surface of the clay, the porous nature of the broken
rock readily admitting water and air. In fact, a more flagrant example
of effecting that which on no account should be done is not easy to
imagine. In treacherous soil the system of tipping an embankment wider
than that required from considerations of lateral and vertical
settlement, and allowing it to stand at a steeper slope than its
permanent angle of repose, and paring down the top unnecessary width is
not to be commended, as the earth is then strained, and the lower
portion is in the looser condition and the toe the weakest part:
however, in the construction of a single line of railway with a narrow
formation width, it is very convenient as affording room for roads for
loaded and empty waggons, and in any soils other than aluminous and
calcareous earths it may be done with impunity, provided all slimy and
slippery surfaces are removed. No side tipping should be allowed in
depositing a new embankment, and any addition of soil to a slope should
be avoided as much as practicable, although in trimming some filling may
be necessary, but the slopes should be rough trimmed by the bank-head
men as the earth is deposited so as to prevent hollows and depressions,
form a comparatively even and regular surface, cause the mass to be
equally exposed to the weather, and prevent any lodgment of water. The
form a tip head naturally assumes will afford some indication of the
stability, for should it be regular and approach a semicircular shape it
shows the earth is of a comparatively uniform character and is subsiding
equally. When it is uneven and jagged, with streaks down the tip, it
indicates unevenness of soil and condition.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account