In embankments to contain or expel water time should always be allowed
for an embankment to consolidate before the admission of the water, but
in the case of a cutting the presence of the navigation water as soon
after construction as practicable may be an advantage, depending upon
the nature of the earth in each case; as it may protect the submerged
portions of the slopes from the deteriorating effects of being in a
constantly changing degree of dryness and wetness, and shield them from
the sun and drying winds. Except under peculiar circumstances the
unstable places will be known in a few months, and provided a canal is
properly constructed, it will not cause much trouble after six months or
a year from earthwork movement if the embankments and cuttings receive
ordinary attention, as the navigation water will quickly indicate the
unconsolidated places. In clay, clay marls, clay loams, and where loamy
soil is intermixed with permeable and water-bearing strata, movement of
the earth in canals will speedily occur unless proper precautions have
been taken in the construction, as they are seldom homogeneous.
Earthworks to contain or expel water should be made proof against even
improbable deterioration and accident, and in proportion as the soil is
less solid and firm it should be consolidated by ramming or other means,
or be covered and protected to prevent it cracking, and only firm and
binding material should be used in canal embankments or those holding or
expelling water in order to prevent slips and subsidences. Chapter II.
treats of some conditions under which slips and subsidences may be
expected. No precaution should be omitted that will render the work
solid and uniform, and nothing should be left to chance. The location is
of great importance, for the earth may vary in stability within a very
short distance, not only in character but as regards the superimposition
of the strata. Upheaved and distorted beds should be avoided, and all
loose and fissured earths, especially rock or other soils having more or
less vertical seams: for all embankments constructed upon fissured soils
are sure to cause anxiety and trouble, and will always be liable to
become in a dangerous state from an excessive rainfall. Impermeable
horizontally deposited earth of considerable thickness is that to be
desired, or firm ground that cannot slide upon another stratum or be
affected by any artificially brought addition to the percolating waters
consequent upon the construction of waterworks. Having carefully
selected a site, which for waterworks purposes must almost invariably be
upon high ground and may have to be upon the top cap soil of a hill and
be peculiarly exposed, the next step to guard against a slip or a
subsidence is to prepare the foundations so that no leakage or trickling
of water can undermine or gradually deteriorate the seat of the
embankment; and, therefore, a thorough connection between the deposited
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account