It might be supposed that in the construction of so many subterranean
ways, in such different sections of the continent, almost every
conceivable geological formation must have been traversed; and so it
appears from Mr. Storrow's report. Granite, quartz, oolite, limestone,
shale, slate, sandstone, gravel, sand, clay and marl, were the material
through which with pick and spade, drill and shovel, the patient workmen
made their way. Not unfrequently, more than half the varieties of rock
and earth we have named were met with in the same tunnel. Sometimes the
work would be interrupted and temporarily abandoned in consequence of an
inundation of water; sometimes enormous masses of gravel and sand would
work through into a shaft or tunnel, with disastrous and, in two
instances, with fatal consequences. In many instances, work was
discontinued for years, for want of funds, and then afterward renewed,
with eventual success. In fact, about the average amount of those
ordinary and inevitable obstacles which stand in the way of all great
enterprises, were encountered by the engineers and contractors, in the
building of these tunnels; but time, money, and skill, never failed to
remove every difficulty. But we propose to extract, and condense from
Mr. Storrow's report, a few of the main facts about some of the most
important of these works; as the report has, not been read, or even seen
by one in a hundred.
The "Box Tunnel" between Chippenham and Bath is more than a mile and
three quarters in length. Nearly one half its length passes through a
kind of limestone rock, and the other through clay, the clay end being
lined with masonry. Five shafts were sunk, the deepest being about three
hundred feet. "During the construction of this tunnel, great
difficulties were encountered from the excessive quantity of water which
inundated the works, sometimes even occasioning their partial
suspension, and powerful means were required to overcome the obstacles.
At one time the water fairly got the mastery over the machinery used for
its removal, and it was only after an additional set of pumps worked by
a fifty horse power engine, that the work could be resumed." This
tunnel was built in five years, and its cost was about $1,750,000, or
about $547 a yard.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account