In the middle of the tunnel line beneath the rails, there is made at the
same time with the excavation, a covered way or drain, in which are laid
the pipes for gas, water, and compressed air. By this drain the waste
water runs off, and it is also intended to serve as a means of escape
for the workmen, in case of a fall of rock, or other accident which
might block up the tunnel. Of course the tunnel must be continually
supplied with fresh air along its whole length, as well as at the
heading. This is easily done from the compressed air tube in the covered
drain.
The whole length of the Mt. Cenis tunnel is through rock varying in
hardness, and veined throughout with quartz. In many parts it is liable
to flake off, and in some places considerable masses have broken away
during the construction. The full section of the tunnel is twenty-six
feet and three inches wide, and twenty feet and eight inches high. The
heading is carried forward about eleven and a half feet wide and nearly
ten feet high. At the time of Mr. Storrow's visit the drilling machines
were used only in the heading. The whole of the enlargement was done by
hand labor in the ordinary way. The drills when brought up to the work
drill eighty holes before any blasting is done. About ninety workmen are
employed at each end. It required from five to seven hours to drill the
eighty holes. Mr. Storrow visited a workshop where some machines were
ready, and a large block of stone was placed in front of them for trial.
The air was let on and a drill put in motion. In 6 1-2 minutes it
drilled 5 1-2 inches. The engineer stated that they would make better
progress than that at the rock in the tunnel. The average progress made
by hand was about sixty-six feet a month. That rate was about doubled by
means of the machines; but since Mr. Storrow's visit these machines have
been greatly improved, and the rate of progress latterly has been about
two hundred feet a month.
The opening of the Mt. Cenis Tunnel was commenced in October, 1857. Up
to July, 1861, about 2142 feet had been excavated, the average progress
being about sixty-six feet a month. The machines were then introduced,
and at the present time, upwards of three miles have been excavated, and
at the rate of progress now being made the tunnel will be completed in
four years. Mr. Storrow's estimate of its cost is $640 per running yard.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account