Building -- Estimates; Factories -- Design and construction; Hardware
Table I shows the approximate cost per cubic foot of various kinds
of structures. In computing the contents of a building, there is no
uniformity in practice, but no great error will be made in figuring the
solid contents from floor of cellar to ridge of roof.
OUTLINE OF THE WORK
=5.= The drawings and specifications of a structure are the guides that
the estimator must follow in making his computations. All measurements
necessary for calculating the quantity of the materials required are
obtained from the drawings; and all information in regard to the
character of the workmanship and the quality of the materials to be
used is furnished by the specifications.
In compiling a schedule, there are three stages to the operation: (1)
Taking the dimensions for each of the various classes of work; (2)
computing and collecting the quantities; and (3) estimating the cost.
In carrying out the first of these steps, each of its subdivisions
should be considered in the order in which the work will be executed in
the building. This order is about as follows:
1. Excavation 8. Joinery
2. Concrete work 9. Hardware and ironwork
3. Stonework 10. Heating and ventilation
4. Brickwork 11. Plumbing and gas-fitting
5. Carpentry 12. Painting and papering
6. Roofing 13. Glazing
7. Plastering
The third step, estimating the cost, may be subdivided into cost of
labor and cost of material. The latter can be definitely fixed by an
examination of lists giving current prices of materials; while the
former must be based on a fixed rate of wages per day for the various
classes of workmen.
The second and third branches of the work, being closely connected with
the first, will be partly considered in connection with it, and, later,
in detail in the complete example on estimating.
ACCURATE ESTIMATING SCHEDULE
=6.= There are so many items to be considered in a careful estimate,
that the estimator should have a list of those coming under each of
the main headings already given, and in compiling a schedule he should
follow this order. The following list, which is arranged to assist in
making an estimate on a dwelling house, will serve as an example of the
general method that should be adopted:
EXCAVATION
Cellar Wells
Areas Pipe trenches
Piers Fence trenches
Privy vaults Grading
Footings Filling
Cesspool Labor
Catch basins
CONCRETE WORK
Cement Wells
Sand Area walls
Broken stone Chimneys
Form lumber Footings
Foundation walls Floors
Partition walls Columns
Piers Pavements
Exterior walls Fences
Concrete blocks Hearths
Concrete cornices Steel reinforcement
Core walls Anchor bolts
Backing Nails and spikes
Cesspools Labor
Tanks
STONEWORK
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account