3. =Alignments and Discharges.=--On the contour map the proposed
alignments of the canal, branches, distributaries, and escapes,
determined after careful consideration of all matters affecting them,
are shown. The tracts to be irrigated by each branch and each
distributary are now marked off, the “irrigation boundaries” following
approximately the valleys and lines of drainage. Any large tracts of
land which cannot be irrigated are of course shown and are excluded.
Forests or other lands which are not to be irrigated should be similarly
dealt with, otherwise confusion is likely to arise later. The commanded
area dependent on each distributary is now ascertained from the map. A
certain percentage being deducted for scattered unculturable areas the
culturable commanded areas are obtained. The proportion to be irrigated
(in India in the kharif) having previously been decided, the number of
acres to be actually irrigated by each distributary is arrived at.
The next step is to ascertain the discharges.[9] A general duty for the
whole canal having been estimated by considering the actual figures for
other canals the full supply of the canal at its head is arrived at.
(CHAPTER I, Art. 6). In Northern India it will be the kharif duty and
kharif full supply. Since some water is lost by absorption in the
channels, the duty of the water on a branch is higher than that of the
whole canal based on its head discharge, and the duty on a distributary
is higher still. In designing a canal, an attempt has to be made to
estimate the losses of water in the main canal and branches, so that the
duties of the branches and distributaries may be estimated and the
channels designed accordingly. On the Western Jumna Canal the figures
were estimated to be as follows:--
Kharif. Rabi.
Average discharge at canal head (c. ft. per sec.) 3536 2755
Duty based on the discharge (acres) 98 138
Estimated loss of water in canal and branches (c. ft. per
sec.) 400 300
Average discharge at distributary head (c. ft. per sec.) 3136 2455
Duty based on the discharge (acres) 111 154
[9] In this Article and in the rest of this Chapter it is assumed that
the canal is a Northern Indian one. Any modifications necessary to
suit canals in other countries will readily suggest themselves.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account