The water level of the distributary with ³⁄₄ full supply, designed so as
to be at least ·5 ft. above the water level in the watercourse heads--or
to be 1 foot above high ground if this simpler plan is adopted--is drawn
on the rough longitudinal section and also the line of F.S., falls being
introduced where desirable and the gradients, F.S. depths of water and
widths of channels being arranged, just as in the case of a canal, so as
to give the required discharges, velocities suited to the soil and a
suitable ratio of depth to velocity. The bed width of a distributary
decreases in whole numbers of feet. The decrease occurs at outlets but
not at every outlet. As the channel becomes smaller its velocity becomes
less and this necessitates, according to the laws of silting and scour,
a reduced depth of water. The height and width of the banks in the tail
portion of a distributary should be made rather greater than
elsewhere--regard being had to the depth and volume of the water--so
that breaches may not occur when the demand abruptly slackens. The
longitudinal section of a distributary should have horizontal lines for
showing the following:
1. Datum |5. Draw-off | 9. Bank width |13. Depth of
| | | digging
2. Bed gradient |6. F.S. discharge|10. Height of |14. Bed level
| | bank |
3. Village |7. Velocity |11. F.S. depth |15. Ground
| | | level[17]
4. Land width |8. V₀ |12. Bed width |16. Chainage[18]
-----------------+-----------------+-----------------+----------------
[17] Called “Natural Surface” in India.
[18] Called “Reduced Distance” in India.
A specimen of a longitudinal section is shown in Fig. 12. It shows only
a few of the above items. In practice all would be shown, large sheets
of paper being used with all the lines and titles printed on them.
When a distributary is constructed the side slopes are made 1 to 1 in
excavation and 1¹⁄₂ to 1 in embankment. The sides usually silt up till
they are ¹⁄₂ to 1 or even vertical. The silting up to ¹⁄₂ to 1 is, as in
the case of a canal, allowed for in the designing. The berms are left so
that, if any part of the side falls in, the bank will not also fall in.
They also allow of widening of the channel. The remarks made in Art. 6
regarding the design of banks, apply to distributaries, especially large
ones.
On a distributary there is seldom much spoil. Where there is no spoil, a
strip of land, outside the bank and 10 feet wide, can be taken up on
either bank from which to obtain earth for repairs. On a minor the width
of the strip is sometimes only 5 feet.
[Illustration: FIG. 12.]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account