By the end of 1828 the directors found they had expended £460,000 on the
works, and that they were still far from completion. They looked at the
loss of interest on this large investment, and began to grumble at the
delay. They desired to see their capital becoming productive; and in the
spring of 1829 they urged the engineer to push on the works with
increased vigour. Mr. Cropper, one of the directors, who took an active
interest in their progress, said to Stephenson one day, “Now, George,
thou must get on with the railway, and have it finished without further
delay; thou must really have it ready for opening by the first day of
January next.” “Consider the heavy character of the works, sir, and how
much we have been delayed by the want of money, not to speak of the
wetness of the weather: it is impossible.” “Impossible!” rejoined
Cropper; “I wish I could get Napoleon to thee—he would tell thee there is
no such word as ‘impossible’ in the vocabulary.” “Tush!” exclaimed
Stephenson, with warmth; “don’t speak to me about Napoleon! Give me men,
money, and materials, and I will do what Napoleon couldn’t do—drive a
railway from Liverpool to Manchester over Chat Moss!”
The works made rapid progress in the course of the year 1829. Double
sets of labourers were employed on Chat Moss and at other points, by
night and day, the night shifts working by torch and fire light; and at
length, the work advancing at all points, the directors saw their way to
the satisfactory completion of the undertaking.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account