The engineer now found that there was nothing for it but to sink numerous
additional shafts over the line of the tunnel at the points at which it
crossed the quicksand, and endeavour to master the water by sheer force
of engines and pumps. The engines erected, possessed an aggregate power
of 160 horses; and they went on pumping for eight successive months,
emptying out an almost incredible quantity of water. It was found that
the water, with which the bed of sand extending over many miles was
charged, was to a certain degree held back by the particles of the sand
itself, and that it could only percolate through at a certain average
rate. It appeared in its flow to take a slanting direction to the
suction of the pumps, the angle of inclination depending upon the
coarseness or fineness of the sand, and regulating the time of the flow.
Hence the distribution of the pumping power at short intervals along the
line of the tunnel had a much greater effect than the concentration of
that power at any one spot. It soon appeared that the water had found
its master. Protected by the pumps, which cleared a space for the
engineering operations—carried on in the midst, as it were, of two almost
perpendicular walls of water and sand on either side—the workmen
proceeded with the building of the tunnel at numerous points. Every
exertion was used to wall in the dangerous parts as quickly as possible;
the excavators and bricklayers labouring night and day until the work was
finished. Even while under the protection of the immense pumping power
above described, it often happened that the bricks were scarcely covered
with cement ready for the setting, ere they were washed quite clean by
the streams of water which poured from overhead. The men were
accordingly under the necessity of holding over their work large whisks
of straw and other appliances to protect the bricks and cement at the
moment of setting.
The quantity of water pumped out of the sand bed during eight months of
incessant pumping, averaged 2,000 gallons per minute, raised from an
average depth of 120 feet. It is difficult to form an adequate idea of
the bulk of the water thus raised, but it may be stated that if allowed
to flow for three hours only, it would fill a lake one acre square to the
depth of one foot, and if allowed to flow for one entire day it would
fill the lake to over eight feet in depth, or sufficient to float vessels
of 100 tons burthen. The water pumped out of the tunnel while the work
was in progress would be nearly equivalent to the contents of the Thames
at high water, between London and Woolwich. It is a curious circumstance
that notwithstanding the quantity thus removed, the level of the surface
of the water in the tunnel was only lowered about 2½ to 3 inches per
week, proving the vast area of the quicksand, which probably extended
along the entire ridge of land under which the railway passed.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account