“Our first work was to examine and disclose the enemy lines of
communication about the Castelletto and Tofana sides, and to gain full
knowledge of their position in detail. In order to accomplish this,
observation points were established which allowed us to carry out such
investigation and to make topographical sketches of the zone. Being as
we were always in the proximity of the enemy, this was a long and
fatiguing work. After a month, however, we succeeded in constructing a
series of positions at short distances from those of the enemy (from
50 to 150 metres). These were provided with cables and rope ladders to
enable us the more rapidly and easily to study (from all possible
points of vantage) the enemy’s positions and the development of his
works.
“The topographic work was begun by taking as a plan metric base
measurement 116 metres of ground on a four-triangle table, which
method enabled making all other drawings based on it. By basing our
findings on this table, we were able to draw up a series of points of
the enemy’s positions. Using the method of successive intersections,
we thus obtained all points of interest to us, as regards direction,
distance and height.
“In addition to this work, executed with the greatest care and
accuracy, we made two independent drawings of the enemy’s positions by
simpler but less exact methods. The first was made with a topographic
compass and Abney level; the other with a Monticole field-square. By
these means we obtained excellent checks on the base system, and so
grounded our work entirely on the trigonometric table and on the
drawings by intersections.
“From the middle of February to the end of March the tools used for
piercing consisted only of mallets and chisels. Our progress was
necessarily slow, yet it was sufficient in this time to give us,
besides 14 metres of tunnel, room for installing the perforating
machinery. At the end of March, notwithstanding heavy snowstorms, the
machinery--some pieces of it weighed as much as 500 and 600 kilos--for
beginning work was installed. This was all brought up by hand, and
without incident.
“The mechanical work was begun on April 2. We utilised two plant as
follows:
“(1) A complete group of benzo-compressors, consisting of a 30-40
horse-power kerosene motor adjusted to a Sullivan compressor by means
of a belt. This machinery was installed, on a solid base of cement, at
the beginning of the tunnel, in a 5 × 8 metre space dug out in the
side of the mountain for that purpose.
“(2) An Ingersoll compressor mounted on a four-wheel truck.
“Both machines were of American manufacture, and gave complete
satisfaction at all times. Each compressed the air to a density of
about seven atmospheres, injecting it into an air-chamber, whence, by
means of a rigid tube, ending in one of flexible rubber, it was
conveyed to the respective drills.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account