The snubbing device consists of an ordinary donkey engine fitted with a
hand brake of extra large size and special air valves so that air is
sucked into the cylinders and let out of the exhaust when the engine is
being pulled backwards by the weight of the load. The load is controlled
by the amount of air let out of the valves. The braking action is very
positive and the load can be stopped in a few revolutions of the crank
shaft.
The average time to lower the load down the incline is three and a half
minutes. At the bottom of the incline, the cable is released and the
truck goes on its way. The cable is attached to the waiting truck by
means of a ring fastened to the frame and the donkey pulls the empty
truck to the top. The time taken to raise the trucks is three minutes.
On grades too steep to operate a truck safely with the ordinary brakes
and yet not steep enough to warrant the expense of the donkey snubber,
the difficulty is overcome by means of a friction snubber. This consists
simply of a cable which is hooked to the truck and extends through a
system of three or four pulleys and thence on down the track. The
friction of this line dragging on the ground and passing through the
pulleys is enough to hold the load so that the truck engine must exert
power to pull the load down the grade. The line is made long enough so
that as the load reaches the bottom of the grade, the free end of the
cable has been pulled up to the system of pulleys and is ready to be
attached to the next load. This system is efficient for small grades, is
inexpensive to install, and requires no further attention.
By the use of the incline with the donkey engine snubber, very heavy
grades can be taken. The construction of the incline is the same as the
rest of the road and is only slightly more expensive to build because of
the inconvenience of laying it on such a steep slope. The use of the
incline will not slow up the operation to any great extent as from fifty
to seventy thousand feet of logs (which is about the average yarding and
loading capacity of one motor-truck side), can be taken over it in a
day. This method of hauling down steep grades is used in several
operations and has been found to be entirely successful.
YARDING
A variety of methods are used by motor truck loggers to get the logs to
the landing to be loaded. The larger operations invariably use the
high-lead method of yarding as the logs come in quicker and with fewer
hang-ups. In a few places the old ground method of yarding with a bull
block is still used. The horse team and skid road is used in a small
timber where poles and piling are being marketed. The latter is a slow
method but will keep one truck busy and is still used in some places
where small stands are located along the highway or in other readily
accessible places.
LOADING AND UNLOADING
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account