River and Canal Engineering, the characteristics of open flowing streams, and the principles and methods to be followed in dealing with them.Bellasis, E. S. (Edward Skelton)
Science
River and Canal Engineering, the characteristics of open flowing streams, and the principles and methods to be followed in dealing with them.
Bellasis, E. S. (Edward Skelton)
Canals; Hydraulic engineering; Rivers
Sometimes the pitching or loose stone is not carried up to the top
of the bank, or even up to high flood-level, and the bank above the
pitching is protected by turfing--the pieces of turf being placed on
edge normally to the slope if very steep (fig. 14) or laid parallel to
the slope if it is not very steep--or, above ordinary water-level, by
plantations of osiers or willows which obstruct the water and tend to
cause silting, and whose roots bind the banks together.
[Illustration: FIG. 16.]
Another method of using fascines is to lay them on the slopes with
their lengths normal to the direction of the stream. The upper end of
a fascine is above low water, and the lower end extends down to the
bed of the stream. Sometimes large ropes made of straw, or rough mats
made of grass, are laid on the slopes and pegged down, or mattresses of
fascines are laid on the slopes and weighted with stones.
[Illustration: FIG. 17.]
A deep recess in the bank (fig. 16) can be filled in, before the
protection is added, with earth well rammed. On the Adige the filling
material consisted (fig. 17) of faggots filled with stones, small cross
dams being made at intervals, as shown by the dotted lines, to arrest
flood water and cause it to deposit silt. At the back of the berm,
poplar or willow slips were planted, and these grew up and their roots
held the bank together. This system succeeded well.
A method of protection which is suitable when the water contains
much silt is what is known in India as bushing. Large leafy branches
of trees are cut and hung, as shown in fig. 18, by ropes to pegs.
They must be closely packed so as not to shake. At first they require
looking after, but silt rapidly deposits and the branches become fixed
and no longer dependent on the ropes. If the work is carefully done,
the result is a smooth, regular, and tenacious berm, as per dotted line
in the figure.
[Illustration: FIG. 18.]
[Illustration: FIG. 19.]
Another method, used on canals, is to make up the bank with earth and
to revet it with twigs or reeds, as shown in fig. 19. The foundation
must be taken down well below bed-level, otherwise the work may slip.
This kind of work cannot be done except when the canal is dry.
If the bank consists of sand or of very sandy soil, it must in any
case have a flat side slope such as 3 to 1. If the sand is in layers
alternating with firm soil, it is a good plan to dig out some of the
sand and to replace it with clods of hard earth.
Staking (fig. 20) may be used, the stakes being one or two feet apart
from centre to centre, and long twigs laid horizontally being passed
in and out of the stakes, or bushing filled in behind the stakes. But
bushing alone is cheaper and nearly as good.
[Illustration: FIG. 20.]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account