In the case of railway bridges across the great shifting rivers of
India, protection used at one time to be afforded by various systems
of spurs. This has now been abandoned in favour of Bell’s guide banks
(fig. 54), which are found to be far more satisfactory. These guide
banks are discussed in the paper by Spring quoted above (_Art. 1_).
The spaces behind the guide banks become filled with water, at least
during floods, and are meant to be silted up. An opening in the
railway embankment should be provided at A, and another on the opposite
side of the river, to ensure a constant flow of water (CHAP. V., _Art.
3_), but they should not be large enough to cause high velocity. The
chief danger to which a guide bank is liable is outflanking when the
stream assumes the position shown. To guard against this danger it is
necessary to have very strong and massive heads to the guide banks.
When the bank of the eroding stream, downstream of the guide bank head,
becomes a semicircle or thereabouts, the stream takes a short-cut
across the sandbank, and to encourage this an artificial cut can be
dug, at the season of low water, on any suitable line.
[Illustration: FIG. 54.]
If the guide banks were made with an increased width of opening at
the upper end, this would reduce the chance of outflanking but would
increase the danger from a direct attack such as indicated, in the
figure, on the left bank. It has been suggested that the width at
the upstream end should be less than at the bridge, but this seems
undesirable. Probably the form shown in fig. 54 is the proper one. The
length of the guide bank upstream of the bridge is made about equal
to the span of the bridge between the two guide banks. If made less
than this, the river might cut into the line of railway. The length of
guide bank downstream of the bridge is generally 300 to 500 feet, being
greater as the velocity of the river is greater and the sand of its bed
finer.
[Illustration: FIG. 55.]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account