River and Canal Engineering, the characteristics of open flowing streams, and the principles and methods to be followed in dealing with them.Bellasis, E. S. (Edward Skelton)
Science
River and Canal Engineering, the characteristics of open flowing streams, and the principles and methods to be followed in dealing with them.
Bellasis, E. S. (Edward Skelton)
Canals; Hydraulic engineering; Rivers
The Bengal Dooars Railway runs near the foot of the Bhutan Himalayas,
and crosses some broad river channels which, after the excessively
heavy rains which occur, are filled by streams of very high velocities.
One such channel or set of channels (fig. 55), more than half a mile
wide, is provided with a bridge whose waterway consists of ten spans
of 60 feet each. The railway embankment across the remainder of the
channel having been breached in many places in 1903, protection was
afforded by T-headed spurs and other groynes, the first arrangement,
which withstood the floods of 1904, being as shown in the figure. The
triangular apex of the A-shaped groyne, south-east of the bridge, was
added in 1905 because, in its absence, the water struck the bridge
obliquely. After the addition there was a great deposit of silt in
the neighbourhood of the four T-headed spurs. Next year the river,
in a great flood, rose over the top of the railway embankment near
these spurs, and finally caused a breach 600 feet wide. The embankment
was afterwards raised. The velocity through the bridge seems to have
approached 18 feet per second. The bridge had at first no floor. A
floor was added, but was much damaged by the floods (_Min. Proc. Inst.
C.E._, vol. clxxiii.). The level of the floor is not given, but it
would seem to have been desirable to make it at a very low level. The
rising of the stream over the railway embankment was attributed to the
silting up near the T-headed spurs. The addition of the triangular
portion above referred to would seem to have somewhat assisted this
process. If all the trouble could have been foreseen, it might have
been best to build an additional bridge 2000 feet south-east of the
existing bridge. The groynes were composed of the wire-network rolls,
described in CHAP. VI., _Art. 3_, piled pyramid fashion.
CHAPTER XII
DRAINAGE AND FLOODS
1. =Preliminary Remarks.=--_Arts. 2_ and _3_ of this Chapter deal
with the calculation of flood discharges, _Art. 2_ dealing with small
streams, in which the water has to be got rid of, and _Art. 3_ with
large streams. The remaining articles discuss the methods of predicting
floods and of preventing them from doing damage. When the discharge
figures have been arrived at in any case, the necessary masonry works
can be designed in accordance with the principles described in CHAPS.
X. and XI. For remarks regarding the design of channels and banks, see
CHAP. IX., _Art. 4_, and also _Art. 6_ of the present Chapter.
In England, land near a stream or flooded area is said to be “awash”
when the flood water rises to within 3 feet of the surface of the
ground. The drainage of such land is apt to be unsatisfactory. If land
is flooded or awash, it may be desirable to shift the outfall of a
branch drain to a point lower down in the main outfall.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account