(_3_) The Sanitary Engineer shall, in all cases, act as adviser of the
local authority.
[Sidenote: Submission of sketch, statement and application.]
[Sidenote: Government of Bihar and Orissa Notification No. 7682M., dated
the 8th July 1913.]
2. When the sketch of the project has been drawn up under Rule 1, and it
is estimated to cost Rs. 10,000 or more, or in the case of an estimate
of less than Rs. 10,000 if the financial assistance of Government is
desired, the local authority shall submit it to the Sanitary Engineer,
who shall make such recommendations as he may think fit. After the
approval of the Sanitary Engineer has been obtained, the sketch project
shall be submitted by the local authority _through the Sanitary Board_
to the Municipal Department of Government, together with a statement
wherein shall be shown the amount of the funds available to meet the
cost of the project, either from current revenue or by way of loan or
from any other source.
In the case of schemes the total estimated cost of which is less than
Rs. 10,000, not being part of a larger scheme and for which financial
assistance from Government is not required, the sanction of Government
need not be obtained, but if the local authorities so desire the scheme
will be examined by the Sanitary Engineer.
[Sidenote: Conditions precedent to grant of administrative approval.]
3. In order to obtain administrative approval to the execution of the
project the local authority shall satisfy Government—
(_1_) that the cost of maintenance of the projected work can be met by
the local authority from revenue;
(_2_) that any loan required to meet the cost of the work can be
repaid, together with the interest thereon, within the period that
may be prescribed by the Government; and
(_3_) that the work can be done effectually in the manner and for the
cost proposed.
[Sidenote: Procedure after grant of administrative approval. Preparation
of detailed plans and estimates.]
4. When the administrative approval of Government has been obtained, and
in no case before, the local authority may arrange for the preparation
of detailed plans and estimates, and for this purpose may—
(_a_) cause the plans and estimates to be prepared by its own officers
or by an officer specially appointed for the purpose and apply to
the Sanitary Engineer for assistance in the selection and
engagement of surveyors to carry out the work; or
(_b_) apply to the Sanitary Board for the services of the Sanitary
Engineer; or
(_c_) apply to Government in the Public Works Department for the
services of their officer; or
(_d_) apply to the District Board for the services of the District
Engineer; or
(_e_) with the previous sanction of the Sanitary Board entrust the
work to a private firm of established reputation.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account