During the winter of 1881 and 1882, the contract was let to Messrs.
Langdon, Sheppard & Co., of Minneapolis, to construct during the working
season of the latter year, or prior to January 1, 1883, 500 miles of
railroad on the western extension of the above company; the contract being
for the grading, bridging, track-laying, and surfacing, also including the
laying of the necessary depot sidings and their grading. The idea that any
such amount of road could be built in that country in that time was looked
upon by the writer hereof, as well as by railroad men generally, as a huge
joke, perpetrated to gull the Canadians. At the time the contract was let,
the Canadian Pacific Railway was in operation to Brandon, the crossing of
the Assiniboine River, 132 miles west of Winnipeg. The track was laid,
however, to a point about 50 miles west of this, and the grading done
generally in an unfinished state for thirty miles further. This was the
condition of things when the contract was entered into to build 500
miles--the east end of the 500-mile contract being at Station 4,660
(Station being at Brandon) and extending west to a few miles beyond the
Saskatchewan River.
The spring of 1882 opened in the most unpromising manner for railroad
operations, being the wettest ever known in that country. Traffic over the
St. Paul, Minneapolis & Manitoba Railroad, between St. Paul and Winnipeg,
was entirely suspended from April 15 to the 28th, owing to the floods on
the Red River at St. Vincent and Emerson, a serious blow to an early
start, as on this single track depended the transportation of all
supplies, men, timber, and contractors' plant, together with all track
materials (except ties), all of these things having to come from or
through St. Paul and Minneapolis. The writer hereof was appointed a
division engineer, and reported at Winnipeg the 15th of April, getting
through on the last train before the St. Vincent flood. No sooner was the
line open from St. Paul to Winnipeg than the cotillon opened between
Winnipeg and Brandon, with a succession of washouts that defied and
defeated all efforts to get trains over, so it was not until the fifth day
of May that I left Winnipeg to take charge of the second division of 30
miles.
By extremely "dizzy" speed I was landed at the end of the track, 180 miles
from Winnipeg, on the evening of the 9th (4 days). My outfit consisted of
three assistant engineers and the necessary paraphernalia for three
complete camps, 30 days' provisions (which turned out to be about 20), 11
carts and ponies, the latter being extremely poor after a winter's diet
on buffalo grass and no grain. On the 18th day of May I had my division
organized and camps in running order. The country was literally under
water, dry ground being the exception, and I look upon the feat of getting
across the country at all as the engineering triumph of my life.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account