The dam of Stubden reservoir, of the Bradford water supply, also on the
millstone grit, was constructed about 1859, and caused considerable
anxiety for a length of time, as leakage occurred in the culvert carrying
the pipes, under the embankment at a point a short distance on the down
stream side of the puddle trench. This was repaired to some extent by
lining with cast iron plates; and an entirely independent outlet was made
by driving a curved tunnel into the hill side clear of the ends of the
dam and lining it with cast iron plates. In this tunnel was then laid the
main of 2 ft. diameter, and as the original culvert again became leaky,
the water had to be lowered, the old masonry pulled out, and the space
filled in with puddle.
The Leeming compensation reservoir of the same water supply, with a dam
of 50 ft. in height, and culvert outlet, had to be treated somewhat in
the same manner, as, although the reservoir had never been filled with
water, in 1875, when it was examined previous to filling, it was found
that the culvert was cracked in all directions; and it was deemed best to
fill it up with Portland cement concrete, and drive a tunnel outlet
through the hill side, as described in the case of the Stubden reservoir.
The Leeshaw dam, which was being constructed at that time upon the same
lines, viz., with culvert outlet under the dam, was, at the advice of Sir
Robert Rawlinson, altered to a side tunnel outlet clear of the dam.
Some years previous to the failure of the Dale Dyke reservoir there
occurred, in 1852, a failure of a similar character--though, as far as
the author is aware, unattended by such disastrous results--at the
Bilberry reservoir at Holmfirth, near Huddersfield, which had never been
filled previous to the day of its failure, and arose from the dam having
sunk, and being allowed to remain at a level actually below that of the
by-wash; so that when the storm occurred, the dam was topped and
destroyed. An after examination proved that the bank was badly
constructed and the foundation imperfect.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account