These methods represent the two extremes of presenting cost estimates.
Each method, or modification thereof, may have its use, dependent on
circumstances.
Reliable cost data are difficult to obtain. Lists of prices of materials
and labor are published in certain engineering and trade periodicals.
The Handbook of Cost Data by H. P. Gillette contains lists of the amount
of material and labor used on certain specific jobs and types of
construction. The price of labor and materials on the local market can
be obtained from the local Chamber of Commerce, contractors and other
employers of labor, and dealers in the desired commodities. Contract
prices for sewerage work published in the construction news sections of
engineering periodicals may be a guide to the judgment of the probable
cost of proposed work, but are generally dangerous to rely upon as full
details are lacking in the description of the work. A wide experience in
the collection and use of cost data is the desirable qualification for
making estimates of cost. It is possessed by few and is not an
infallible aid to the judgment.
Having completed the design and summary of the bills of material and
labor necessary for each structure or portion of the sewerage system,
the product of the unit cost and the amount of each item plus an
allowance for overhead will equal the cost of the item. The total cost
will be the sum of the costs of each item. The items should be so
grouped that the cost of the different portions of the system are
separated in order that the effect on the total cost resulting from
different combinations of items or the omission of any one item may be
readily computed.
A method for estimating the approximate cost of sewers, devised by W. G.
Kirchoffer[13] depends upon the use of the diagram shown in Fig. 2. The
factors for local conditions are shown in Table 2. For example, let it
be required to find the cost of a 15–inch vitrified pipe sewer at a
depth of 9 feet, if the unit costs of labor and material and the
conditions are the same as shown in Table 3.
[Illustration:
FIG. 2.—Diagram for Estimating the Cost of Sewers.
Eng. News, Vol. 76, p. 781.
]
_Solution_
First: To find the factor depending on local conditions, enter the
diagram at the 10–inch diameter and continue down until the
intersection with the depth of trench at 8.2 feet is found. Now go
diagonally parallel to lines running from left to right upwards to
the intersection with the vertical line through a cost of 45 cents
per foot. The diagonal line running from left to right downwards
through this intersection corresponds to a factor of about 11.
TABLE 2
FACTORS FOR COSTS OF SEWERS TO BE USED WITH FIGURE 2
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account