=160. Final Line and Grade.=—After the excavation of the trench has
proceeded to within a foot or two of the final depth, the grade and line
are transferred to markers supported over the center of the trench. The
markers are horizontal boards spanning the trench and held in position
either by nails driven into stakes at the side of the trench, by nails
driven into the sheeting, or by weights holding the boards on the
ground. Two stakes driven in the ground at the side of the trench as
shown in Fig. 113 are the common method of support. If the banks are too
weak to stand under the jarring of the driving of the stakes, or
pavement or other causes prevent their use the horizontal cross piece
may be weighted down by bricks or a bank of earth. The cross pieces are
located about every 25 feet along the trench and at any convenient
distance above the surface of the ground. The nearer the ground the
stronger the support but the greater the interference with work in the
trench. The center line of the sewer is marked on the cross pieces after
they are set, and vertical struts are nailed on them with one edge of
the strut straight, vertical, and on the center line as shown in Fig. 1.
The corresponding edge should be used on all struts in order to avoid
confusion. The edge is placed in a vertical position by means of a plumb
bob or carpenter’s level.
[Illustration:
FIG. 113.—Methods for the Support of the Grade Line.
]
The cut to the invert of the sewer is recorded to an even number of feet
where practicable by driving a nail in the upright strut so that the top
edge of the nail is at the desired elevation above the sewer, or the
upright is nailed with its top at the proper number of feet above the
sewer invert. The cut is marked on the upright in feet, tenths, and
hundredths from the recorded point to the elevation of the invert.
The inspector should watch these grade markers with care by sighting
back along them to see that they are in line and have not moved. In
quicksand or caving material the marks may move during the setting of
the pipes and the levelman should be on the job constantly.
When excavation is being done by machine the depth of the excavation is
controlled by the operator who maintains a sighting rod on the machine
in line with the grade marks on the uprights.
[Illustration:
FIG. 114.—Diagram Showing the Use of the Grade Rod for Fixing the
Elevation of a Sewer.
]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account