=161. Transferring Grade and Line to the Pipe.=—In transferring grade
and line to the sewer a light strong string is stretched tightly from
nail to nail on the uprights marking the line and grade. A rod with a
right angle projection at the lower end, as shown in Fig. 114, is marked
with chalk or a notch at such a distance from the end that when the mark
is held on the grade cord the lower portion of the rod which projects
into the pipe will rest on the invert. The pipe is placed in line by
hanging a plumb bob so that the plumb bob string touches the grade and
center line cord. These marks are taken only as frequently as may be
necessary to keep the sewer in line. An experienced workman can maintain
the line by eye for considerable distances. Measurements should never be
taken to the top of the pipe in order to determine position and grade as
the variations in the diameter of the pipe may cause appreciable errors.
The position and elevation of the forms for brick, concrete, and unit
block sewers are located by reference to the grade line, or they may be
placed under the immediate direction of the survey party, or by
specially located stakes. For large sewers requiring deep and wide
excavation the grade and line stakes are driven in the bottom of the
trench about a foot above the finished grade. This requires the constant
presence of an engineer who is usually available on work of such
magnitude.
=162. Line and Grade in Tunnel.=—In tunnels, line and grade are given by
nails driven in the roof, the progress of excavation or the shield being
followed by eye and the forms set by direct measurement to the nails.
TUNNELING
=163. Depth.=—The depth at which it becomes economical to tunnel depends
mainly upon the character of the material to be excavated and on the
surface conditions. In soft dry material with unobstructed working space
at the surface, open cut may be desirable to depths as great as 35 or 40
feet. Tunnels are cut in rock at depths of 15 feet or less. In some very
wet and running quicksand encountered in the construction of sewers for
the Sanitary District of Chicago it was found economical to tunnel at
depths of 20 feet and less. Crowded conditions on the surface, expensive
pavements, or extensive underground structures near the surface may make
it advantageous to tunnel at shallower depths than would otherwise be
economical. Winter is the best season for tunneling as the workmen are
protected from the elements and labor is more plentiful.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account