=166. Shields.=—Shields are used in tunneling in soft wet material and
are particularly suitable for work under air pressure. They are used in
rock tunnels where water is anticipated or air pressure is used. The
shields often save the expense and difficulty of timbering as the
masonry of the sewer follows closely behind the shield. Fig. 118 shows
the arrangement for a shield for tunneling in soft material in the
construction of the Milwaukee sewers. The shield has an exterior
diameter of 9 feet 4 inches and an overall length of 9 feet 8⅛ inches.
The cutting edge section is 20 inches long. The shell is made of one
inch plate to the back of the jack chambers and one-half inch plate in
the tail. The shield is driven by ten 60–ton hydraulic jacks. The jacks
are shown in position in the figure. These jacks rest against the
finished tunnel lining and serve to consolidate it at the same time that
they push the shield into the material to be excavated. The face of the
tunnel is cut with a pick and shovel while the jacks are removed one at
a time and a new ring of lining is put in place. The lining may be
temporary timbering to receive the thrust of the jacks, but it is
usually desirable that the permanent lining follow immediately behind
the shield. Since the shield is larger than the outside of the lining
the space left by its passage should be grouted immediately after it has
passed.
=167. Tunnel Machines.=—Tunnel machines have been used successfully on
sewer tunnels in soft materials, but not in rock.[95] The machines are
of different types, but in general consist of a revolving cutting head,
equipped with knives, and driven by an electric motor. The bearing on
which the shaft for the cutting head rests is supported against the
sides of the tunnel. The muck is carried away by means of a conveyor and
dumped into muck cars without rehandling. Rapid progress can be made
with these machines in suitable conditions.
[Illustration:
FIG. 119.—Method of Drilling and Loading Rock Tunnel Face.
Courtesy, Aetna Power Co.
]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account