One man can pour about 33 eight-inch joints, and two men can complete
about 26 twelve-inch joints per hour on the bank where conditions are
more or less fixed.
=182. Labor and Progress.=—The labor required for the laying of pipe
sewers, exclusive of excavation, bracing and backfilling, consists of
pipe layers and helpers. For pipes 24 to 27 inches in diameter or
smaller one pipe layer and one or more helpers are necessary, dependent
on the size of the pipe and the depth of the trench. For larger pipes
two pipe layers can work economically each working on one-half of the
pipe and making half of the joint. The speed of pipe laying is
ordinarily limited by the speed of the excavation, but on a job in
Topeka, Kan.,[100] where the average day’s progress with a machine
excavator was 200 to 500 feet of trench per day, the pace was limited by
the speed of the pipe laying gang. This gang consisted of two pipe
layers in the trench and two helpers on the surface. The sizes of pipes
handled were from 8 to 27 inches.
BRICK AND BLOCK SEWERS
=183. The Invert.=—In good firm ground the excavation is cut to the
shape of the sewer and the bricks are laid directly on the ground, being
embedded in a thick layer of mortar. After the foundation has been
prepared and before the bricks are laid, two wooden templates, called
profiles, are prepared, similar to that shown in Fig. 126, to conform to
the shape of the inside and outside of the sewer. Each course of bricks
is represented by a row of nails in the profile and each nail
corresponds to a joint in the row. The two profiles are set true to line
and grade. A cord is stretched tightly between the two lowest nails on
opposite templates and a row of bricks is laid. The bricks are laid
radially and on edge with their long dimension parallel to the axis of
the sewer and with one edge just touching the string. As each one or two
or three rows are completed the guide line is moved up to the next
nails. When the bricks are laid on the ground all but large depressions
are filled in with tamped sand or mortar by the masons. Approximately
the same number of rows of bricks is kept completed on either side of
the center line. The succeeding courses follow within three to five rows
of each other, the only bond between courses being the mortar joint.
This is called row lock bond and with few exceptions has been used on
all brick sewers in the United States. As the sides of the sewer become
higher during the construction, platforms must be built for the masons.
These platforms are built of wood and rest directly on the green
brickwork. They should be designed to spread the load as much as
possible. The brickwork of the invert is continued up in this way to the
springing line. As soon as one section is completed one profile is moved
10 to 20 feet ahead along the trench according to the standard length of
sections, and set in position. The line is then strung from it to nails
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account