The sewer section may be built as a monolith, in two parts, or in three
parts. In casting the sewer as a monolith the complete full round inside
form is fixed in place by concrete blocks and wires. The full round
outside form is completed as far as possible without interfering too
much with the placing and tamping of the concrete. The concrete is
poured from the top, being kept at the same height on each side of the
form, and tamped while being poured. The remaining panels of the outside
form are placed in position as the concrete rises to them. An opening is
left at the top of the outside arch forms which is of such a width that
the concrete will stand without support. The casting of sewers as a
monolith is difficult and is usually undesirable because of the
uncertainty of the quality of the work. It has the advantage, however,
of eliminating longitudinal working joints in the sewers which may allow
the entrance of water or act as a line of weakness.
[Illustration:
FIG. 130.—Construction Joints for Concrete Sewers.
]
If the sewer is to be cast in two sections the invert is poured to the
springing line or higher. A triangular or rectangular timber is set in
the top of the wet concrete as shown in Fig. 130. When the concrete has
set the timber is removed and the groove thus left forms a working joint
with the arch. After the invert concrete has set, the arch centering is
placed and the arch is completed. This is the most common method for the
construction of medium-sized circular sewers.
Large sewers with relatively flat bottoms are poured in two or three
sections. First the invert is poured without forms and is shaped with a
screed. About 6 inches of vertical wall is poured at the same time. This
acts as a support for the side-wall forms. The side walls reach to the
springing line of the arch and are poured after the invert has set. At
the third pouring the arch is completed. The sewer shown in Fig. 1 is
being poured in two steps, as the side walls are so low that they are
poured at the same time as the invert. A transverse working joint
similar to one of the types used in Fig. 130 is set between each day’s
work.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account