Placing concrete in Arch. The steel lagging of the forms is carried up
in sections as the concrete is deposited. The drain is horseshoe
shaped, and is 12 feet 3 inches high and 12 feet 3 inches wide.
]
The end of the concrete conveying pipe is provided with a flexible joint
the simplest form of which can be made by slipping a section of pipe of
larger diameter over the end of the transmission line. The concrete is
deposited directly on the invert or into the side-wall forms and can be
blown into the arch forms for 20 to 25 feet.
=190. Materials for Forms.=—The materials used in forms for concrete
sewers are: wood, wood with steel lining, and steel alone. The first
cost of wood forms is lower than that of steel but their life is
relatively short. If the forms are to be used a number of times steel is
more economical. With proper care and repairs steel forms will outlast
any other material. Because of the increasing price of lumber and
improvements in steel forms, wood forms are not frequently used. A
common type of specification under which forms are used is:
The material of the forms shall be of sufficient thickness and the
frames holding the forms shall be of sufficient strength so that
the forms shall be unyielding during the process of filling. The
face of the form next to the concrete shall be smooth. If wooden
forms are used the planking forming the lining shall invariably be
fastened to the studding in horizontal lines, the ends of these
planks shall be neatly butted against each other, and the inner
surface of the form shall be as nearly as possible perfectly
smooth, without crevices or offsets between the ends of adjacent
planks. Where forms are used a second time, they shall be freshly
jointed so as to make a perfectly smooth finish to the concrete.
All forms shall be water-tight and shall be wetted before using.
Any material in contact with wet concrete should be oiled or greased
beforehand in order to prevent adherence to the concrete.
=191. Design of Forms.=—The design of forms for reinforced concrete work
requires some knowledge of the strength of materials and the theories of
beams, columns, and arches. Forms can be constructed without such
knowledge but that they will be both economical and adequate is an
improbability. The ordinary beam and column formulas are applicable to
the design of forms. The maximum bending moment for sheeting and ribs is
taken as (_wl_^2)⁄8, where _w_ is the load per unit length, and _l_ is
the length between supports. Sanford Thompson recommends that the
deflection be calculated as (_wl_^3)⁄(128_EI_), in which _E_ is the
modulus of elasticity of the material, and _I_ is the moment of inertia
of the cross-section referred to the neutral axis. The horizontal
pressure of the concrete against the forms has been expressed
empirically by E. B. Smith,[101] as
_P_ = _H_^{0.2}_R_^{0.3} + 120_C_ − 0.3_S_
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account